Feedack Description
No progress regarding filling of side patari .neither filling earth caused here is huse waterloging occure nor uplifting of road level so that road water drain out into the drain constructed .
Landmark: Village pherupur , laksar road , haridwar
As Per Google Address : 01, Laksar Rd, Alipur Ibrahimpur, Pherupur Ramkhera, Pherupur, Uttarakhand 249404, India
Submitted By : -
Satish chauhan , 4 Feebacks
On 07 Feb 2024
29.857814102434N 78.116679657251E
Division Segment ID : 5726 at Chainage 9.022
Purkazi Laksar Haridwar national highway
Identified By Kml
Nearby complaints and Distance(m)
within: m
acknowledged avg 20 H : 47 M
1 hour
14 minute
assigned avg 1 D : 6 H : 31 M
1 day
8 hour
1 minute
completed avg 2 D : 14 H : 48 M
1 day
18 hour
36 minute
closed avg 2 D : 22 H : 13 M
1 day
18 hour
57 minute
Status Time Line
acknowledged
on 07 Feb 2024
03:51 PM
By
Amit Kumar Tyagi
(010093234)
assigned
on 07 Feb 2024
03:51 PM
By
Amit Kumar Tyagi
(010093234)
(assigned to Rajeev Kumar (65006309))
completed
on 07 Feb 2024
04:16 PM
By
Rajeev Kumar
(65006309)
with Comment "The complaint is not related to patch repair. Construction work is in progress."
assigned
on 08 Feb 2024
10:38 PM
By
Deepak Gupta
(420010315)
(assigned to Rajeev Kumar (65006309))
completed
on 09 Feb 2024
09:12 AM
By
Rajeev Kumar
(65006309)
with Comment "This is an under construction site whose completion date is July 2024. At present the work of GSB is in progress, the work of BC will be done soon. The shoulder will be built after the BC work. So This complaint is not related to the patch repair."
closed
on 09 Feb 2024
09:33 AM
By
Deepak Gupta
(420010315)
with Comment "The captioned site is water logged area in about 500 m. Under sanctioned work, construction of drain & laying of GSB& dressing of pattrie is under progress. Bituminous work will start on suitable weather. The completion date as per the agreement is in the month of July 2024."