MISPWD Complaint Details
  • Individual Patch Reporting Event

Feedback ID: 1867

Current Status: closed

Office: CD Pokhari

District: Chamoli

Feedack Description

Water logging and road damage

Landmark: Pokhari road devtoli
As Per Google Address : 7688+3JG, Karanprayag Main Bazar Rd, Karnaprayag, Uttarakhand 246446, India

Submitted By : -

Amit , 4 Feebacks

On 29 Jul 2024

30.26519897N 79.21637637E

Division Segment ID : 5679 at Chainage 25.263

Karanprayag Pokhari Gopeshwer state highway

Identified By Kml

Nearby complaints and Distance(m)

within: m

acknowledged avg 20 H : 47 M

2 day

16 hour

44 minute

assigned avg 1 D : 6 H : 31 M

2 day

16 hour

45 minute

completed avg 2 D : 14 H : 48 M

2 day

17 hour

19 minute

closed avg 2 D : 22 H : 13 M

8 day

17 hour

51 minute

Status Time Line

  • 29 Jul 2024 (3 months ago) Received

  • 01 Aug 2024 (3 months ago) acknowledged

  • 01 Aug 2024 (3 months ago) assigned

  • 01 Aug 2024 (3 months ago) completed

  • 07 Aug 2024 (3 months ago) closed

  • acknowledged on 01 Aug 2024 02:04 PM
    By Sunil Kumar (42270213M00022)

  • assigned on 01 Aug 2024 02:05 PM
    By Sunil Kumar (42270213M00022) (assigned to Krishan Kumar (42270213M01374)) with Comment "Resolve the complaint"

  • completed on 01 Aug 2024 02:39 PM
    By Krishan Kumar (42270213M01374) with Comment "Work is completed temporarily by filling pot holes by WBM screening material .BM/SDBC work sanctioned in Pokhri-Karnprayag m/r under CRIF. The patch work will be completed permanently by BM work after monsoon season in the month of October.Sorry for the inconvenience."

  • closed on 07 Aug 2024 03:11 PM
    By Krishan Kumar (42270213M01374) with Comment "The water logging issue and patches in the Pokhri-karnprayag motor road in km 25 near Degree College Karanprayag due to construction of scupper not started near College.The scupper was not constructed due to hindrance of water pipe line in the construction area of the scupper and some public issue.The hindrance of water pipeline and other issues is solved with the help of administrative and police department on 07-08-2024.After the completion of scupper,the complete bituminous work in km 25 of this road(under Crif yojna) will be started in the month of October after rainy season."

Images of Issue Uploaded:
Images of Resolve Uploaded: