Feedack Description
एक वर्ष में ही टूट गई पूरी बिचवा तक टूटी है
Landmark: प्रीती सिलाई सेंटर के सामने कंजाबाग पटिया खटीमा उधम सिंह नगर
As Per Google Address : Devbhoomi Complex, Kanjabag Road, Khatima, Uttarakhand 262308, India
Submitted By : -
Trilok singh jora , 1 Feeback
On 20 May 2023
Nearby complaints and Distance(m)
within: m
acknowledged avg 20 H : 47 M
1 hour
8 minute
assigned avg 1 D : 6 H : 31 M
8 day
22 hour
34 minute
completed avg 2 D : 14 H : 48 M
10 day
16 hour
14 minute
closed avg 2 D : 22 H : 13 M
16 day
20 hour
23 minute
Status Time Line
acknowledged
on 20 May 2023
08:42 PM
By
Mohan Chandra
(75007993)
assigned
on 20 May 2023
08:43 PM
By
Mohan Chandra
(75007993)
(assigned to Prem Prakash Tewari (080014890))
completed
on 29 May 2023
05:50 PM
By
Prem Prakash Tewari
(080014890)
assigned
on 29 May 2023
06:08 PM
By
Mohan Chandra
(75007993)
(assigned to Prem Prakash Tewari (080014890))
completed
on 31 May 2023
11:48 AM
By
Prem Prakash Tewari
(080014890)
with Comment "Excavation in pattri of the road is done by World Bank Project Unit Payjal Nigam Haldwani for laying of water supply Pipe line hence the road got damaged in some part. The distribution of water supply connection and testing of pipe line is pending by Payjal Nigam. Therefore the repair of the road will be done after completion of work by Payjal Nigam."
closed
on 06 Jun 2023
03:58 PM
By
Mohan Chandra
(75007993)
with Comment "Earthen shoulder of Road is damaged during laying of water supply lines by Water Supply Department underJal Jeewan Mission. Patries will be dressed after water supply lines tested by concerned department"