# | Work Type | Road (Km) | Bridge (No) | Bridge (Span in m) | Building (No) | Job (No) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Remining | Target | Achivement | Remining | Target | Achivement | Remining | Target | Achivement | Remining | Target | Achivement | Remining | Target | Achivement | ||
1 | First Phase | 0.000 | 0.000 | 0.000 | 0 | 0 | 0 | 0.000 | 0.000 | 0.000 | 0 | 0 | 0 | 0 | 0 | 0 |
2 | New Road (Stage I & II) | 13.500 | 4.000 | 0.000 | 0 | 0 | 0 | 0.000 | 0.000 | 0.000 | 0 | 0 | 0 | 0 | 0 | 0 |
3 | Reconstruction | 3.700 | 3.000 | 0.000 | 0 | 0 | 0 | 0.000 | 0.000 | 0.000 | 0 | 0 | 0 | 0 | 0 | 0 |
4 | New Road (Stage I) | 9.100 | 3.900 | 0.000 | 0 | 0 | 0 | 0.000 | 0.000 | 0.000 | 0 | 0 | 0 | 0 | 0 | 0 |
5 | New Road (Stage II) | 1.000 | 2.000 | 0.000 | 0 | 1 | 0 | 0.000 | 18.000 | 0.000 | 0 | 0 | 0 | 0 | 0 | 0 |
Total | 27.3 | 12.9 | 0 | 0 | 1 | 0 | 0 | 18 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |