Office :

All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 3 78.74 13.00 30.00 01 Oct 2024 15 Oct 2024 13.00 17.00 130.77 %
MDR 5 135.74 30.00 48.00 01 Oct 2024 15 Oct 2024 30.00 35.00 116.67 %
8 214.48 43.00 78.00 43.00 52.00 120.93 %
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 PD Almora SH 5484 काठगोदाम (रानीबाग) भीमताल खुटानी चांफी पदमपुरी धानाचूली पहाड़पानी शहरफाटक मौरनौला देवीधुरा लोहाघाट पंचेश्वर राज्य मार्ग [ Ch. 61.000 - 92.400] 31.400 3.000 6.00 01 Oct 12 Oct 3.000 5.00 167 16 Oct 20:49 pm Puran Singh Fartyal, Assistant Engineer Civil, PD Almora
2 PD Almora SH 5586 अल्मोड़ा शहरफाटक राज्य मार्ग [ Ch. 0.000 - 42.042] 42.042 6.000 16.00 01 Oct 15 Oct 6.000 8.00 133 14 Oct 09:36 am Manoj Kumar, Assistant Engineer Civil, PD Almora 2
3 PD Almora SH 5584 अल्मोड़ा बागेश्वर मोटर राज्य मार्ग [ Ch. 0.000 - 5.300] 5.300 4.000 8.00 01 Oct 14 Oct 4.000 4.00 100 13 Oct 23:04 pm Hitesh Kandpal, Executive Engineer Civil, Engineer-in-Chief Office
4 PD Almora MDR 2 अल्मोड़ा पौधार रामेश्वर सम्पर्क मोटर मार्ग [ Ch. 0.000 - 9.550] 9.550 5.000 13.00 01 Oct 15 Oct 5.000 8.00 160 16 Oct 19:00 pm Manoj Kumar, Assistant Engineer Civil, PD Almora
5 PD Almora MDR 61 कोसी खूंट शीतलाखेत कठपुड़िया दौलाघाट मोटर मार्ग [ Ch. 0.000 - 38.540] 38.540 6.000 10.00 01 Oct 15 Oct 6.000 7.00 117 17 Oct 16:26 pm Kundan Giri Goswami, Assistant Engineer Civil, PD Almora 1
6 PD Almora MDR 64 द्वारसों काकड़ीधाट मोटर मार्ग (द्वारसों से ) [ Ch. 0.000 - 46.500] 46.500 7.000 12.00 01 Oct 15 Oct 7.000 7.00 100 17 Oct 16:26 pm Kundan Giri Goswami, Assistant Engineer Civil, PD Almora 1
7 PD Almora MDR 5643 मजखाली सोमेश्वर मोटर मार्ग [ Ch. 0.000 - 23.600] 23.600 7.000 7.00 01 Oct 15 Oct 7.000 7.00 100 18 Oct 13:31 pm Kundan Giri Goswami, Assistant Engineer Civil, PD Almora 24
8 PD Almora MDR 5638 कोसी दौलाधाट कोरीछीना बग्वाली पोखर बिन्ता मोटर मार्ग [ Ch. 0.000 - 17.550] 17.550 5.000 6.00 01 Oct 15 Oct 5.000 6.00 120 17 Oct 16:27 pm Kundan Giri Goswami, Assistant Engineer Civil, PD Almora 5