Office :

All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 4 154.64 59.00 95.00 01 Oct 2024 31 Oct 2024 59.00 65.00 110.17 %
MDR 5 103.01 52.00 91.00 01 Oct 2024 31 Oct 2024 52.00 53.00 101.92 %
ODR 4 32.50 26.50 50.00 01 Oct 2024 29 Oct 2024 26.50 26.50 100.00 %
13 290.14 137.50 236.00 137.50 144.50 105.09 %
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 CD Almora SH 5490 लोहाघाट बाराकोट सिमलखेत काफलीखान भनोली राज्य मार्ग [ Ch. 38.120 - 80.645] 42.525 16.000 20.00 01 Oct 31 Oct 16.000 18.00 113 15 Oct 17:53 pm Alok Kumar Oli, Assistant Engineer Civil, CD Almora
2 CD Almora SH 5424 अल्मोड़ा बेरीनाग अस्कोट राज्य मार्ग [ Ch. 1.400 - 44.100] 42.700 16.000 30.00 01 Oct 30 Oct 16.000 16.00 100 18 Oct 07:41 am Harish Chandra Joshi, Assistant Engineer Civil, CD Almora 2
3 CD Almora MDR 5671 एन0टी0डी0 कफड़खान धौलछीना मोटर मार्ग [ Ch. 0.000 - 23.892] 23.892 4.000 10.00 01 Oct 25 Oct 4.000 5.00 125 14 Oct 17:10 pm Harish Chandra Joshi, Assistant Engineer Civil, CD Almora
4 CD Almora MDR 5672 आरतोला जागेश्वर नैनी मोटर मार्ग [ Ch. 0.000 - 20.410] 20.410 15.000 25.00 01 Oct 30 Oct 15.000 15.00 100 18 Oct 07:34 am Alok Kumar Oli, Assistant Engineer Civil, CD Almora
5 CD Almora MDR 7866 कोसी दौलाधाट कोरीछीना बग्वाली पोखर बिन्ता मोटर मार्ग [ Ch. 17.550 - 38.650] 21.100 12.000 18.00 01 Oct 30 Oct 12.000 12.00 100 22 Oct 14:00 pm Dwarika Prasad Verma, Assistant Engineer Civil, CD Almora
6 CD Almora MDR 5769 धौलादेवी खेती जटेश्वर धुरागॉव सेराघाट मोटर मार्ग [ Ch. 0.000 - 29.605] 29.605 17.000 30.00 01 Oct 31 Oct 17.000 17.00 100 18 Oct 07:31 am Harish Chandra Joshi, Assistant Engineer Civil, CD Almora
7 CD Almora MDR 5768 कारीछीना बग्वालीपोखर-गगास मोटर मार्ग [ Ch. 0.000 - 8.000] 8.000 4.000 8.00 01 Oct 17 Oct 4.000 4.00 100 22 Oct 15:07 pm Dwarika Prasad Verma, Assistant Engineer Civil, CD Almora
8 CD Almora ODR 5772 पिलखा पाटिया मोटर मार्ग [ Ch. 0.000 - 9.000] 9.000 9.000 15.00 01 Oct 29 Oct 9.000 9.00 100 17 Oct 13:04 pm Suresh Chandra Pauriyal, Assistant Engineer Civil, CD Almora 2
9 CD Almora ODR 5773 बसोलीखान चमतोला मोटर मार्ग [ Ch. 0.000 - 3.500] 3.500 3.500 15.00 01 Oct 29 Oct 3.500 3.50 100 16 Oct 08:03 am Alok Kumar Oli, Assistant Engineer Civil, CD Almora
10 CD Almora ODR 5775 ताकुला गणानाथ रनमन मोटर मार्ग [ Ch. 0.000 - 6.000] 6.000 6.000 10.00 01 Oct 28 Oct 6.000 6.00 100 17 Oct 15:27 pm Suresh Chandra Pauriyal, Assistant Engineer Civil, CD Almora 3
11 CD Almora ODR 5776 गणानाथ नाईम मरछीना पातलीबगड़ मोटर मार्ग [ Ch. 0.000 - 14.000] 14.000 8.000 10.00 01 Oct 29 Oct 8.000 8.00 100 15 Oct 14:24 pm Suresh Chandra Pauriyal, Assistant Engineer Civil, CD Almora 3
12 CD Almora SH 5430 बागेश्वर गिरेछीना सोमेश्वर द्वाराहाट विमाण्डेश्वर ईड़ा रानीखेत राज्य मार्ग [ Ch. 20.000 - 50.410] 30.410 15.000 25.00 11 Oct 15 Oct 15.000 15.00 100 15 Oct 12:17 pm Dwarika Prasad Verma, Assistant Engineer Civil, CD Almora 1
13 CD Almora SH 5478 कर्णप्रयाग(सिमली) ग्वालदम बागेश्वर चकोड़ी थल मुनस्यारी जौलजीवी राज्य मार्ग [ Ch. 12.000 - 51.000] 39.000 12.000 20.00 11 Oct 15 Oct 12.000 16.00 133 15 Oct 13:46 pm Dwarika Prasad Verma, Assistant Engineer Civil, CD Almora 11