Division | Type | ID | Name | Total Length | Target Length | Amount | Planned Start | Planned End | Till Date Target | Progress | % | Progress On | Progress By | Images | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | CD Kapkot | MDR | 270 | खडलेख भनार नाचनी मोटर मार्ग [ Ch. 0.000 - 8.000] | 8.000 | 7.000 | 8.00 | 01 Oct | 31 Oct | 7.000 | 7.00 | 100 | 15 Oct 15:06 pm | Gajender Singh, Assistant Engineer Civil, CD Kapkot | 23 |