Office :

All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 2 28.30 9.00 9.00 01 Oct 2024 30 Oct 2024 9.00 9.00 100.00 %
MDR 1 11.75 7.00 7.50 01 Oct 2024 30 Oct 2024 7.00 7.00 100.00 %
ODR 1 11.00 7.00 5.00 01 Oct 2024 30 Oct 2024 7.00 7.00 100.00 %
4 51.05 23.00 21.50 23.00 23.00 100.00 %
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 PD Gopeshwar SH 5470 जोशीमठ सिंहधार नृसिंह मंदिर राज्य मार्ग [ Ch. 0.000 - 3.900] 3.900 3.000 4.00 01 Oct 30 Oct 3.000 3.00 100 14 Oct 18:15 pm Dhananjay Verma, Assistant Engineer Civil, PD Haridwar 10
2 PD Gopeshwar SH 5521 रुद्रप्रयाग पोखरी गोपेश्वर राज्य मार्ग [ Ch. 87.320 - 111.720] 24.400 6.000 5.00 01 Oct 30 Oct 6.000 6.00 100 15 Oct 16:15 pm Rajbeer Singh Chauhan, Executive Engineer Civil, PD Gopeshwar 31
3 PD Gopeshwar MDR 5956 स्वतंत्रता संग्राम सेनानी शहीद बुद्धि सिंह पंवार लीसा फैक्ट्री गोपेश्वर देवरखड़ोरा मोटर मार्ग [ Ch. 0.000 - 11.750] 11.750 7.000 7.50 01 Oct 30 Oct 7.000 7.00 100 17 Oct 17:31 pm Umesh Dharia, Assistant Engineer Civil, PD Gopeshwar 1
4 PD Gopeshwar ODR 341 नन्दप्रयाग चमोली वाया सावरीसैंण मोटर मार्ग (चारधाम यात्रा का वैकल्पिक मार्ग ) [ Ch. 0.000 - 11.000] 11.000 7.000 5.00 01 Oct 30 Oct 7.000 7.00 100 17 Oct 16:50 pm Prashant Rawat, Assistant Engineer Civil, Engineer-in-Chief Office 9