All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 3 108.09 45.00 64.00 01 Oct 2024 31 Oct 2024 45.00 45.00 100.00 %
MDR 2 29.33 5.30 8.00 01 Oct 2024 03 Oct 2024 5.30 6.75 127.36 %
ODR 2 4.30 4.30 12.00 01 Oct 2024 03 Oct 2024 4.30 4.30 100.00 %
7 141.72 54.60 84.00 54.60 56.05 102.66 %
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 PD Nainital SH 5512 नैनीताल कालाढूगी बाजपुर दोराहा राज्य मार्ग [ Ch. 0.000 - 31.660] 31.660 20.000 20.00 01 Oct 31 Oct 20.000 20.00 100 16 Oct 09:14 am Manoj Kumar Pande, Assistant Engineer Civil, PD Nainital
2 PD Nainital SH 5440 भवाली नैनीताल टॉकी किलबरी पंगोट किलबरी राज्य मार्ग [ Ch. 0.000 - 26.430] 26.430 18.000 30.00 01 Oct 31 Oct 18.000 18.00 100 16 Oct 09:15 am Manoj Kumar Pande, Assistant Engineer Civil, PD Nainital
3 PD Nainital SH 432 काठगोदाम हैड़ाखान साननी बैण्ड सिमलिया बैण्ड राज्य मार्ग [ Ch. 0.000 - 50.000] 50.000 7.000 14.00 01 Oct 03 Oct 7.000 7.00 100 13 Oct 08:01 am Govind Singh Janoti, Assistant Engineer Civil, PD Nainital 2
4 PD Nainital MDR 7848 अमृतपुर बनना बबियाड़ मोटर मार्ग [ Ch. 0.000 - 22.825] 22.825 2.300 6.00 01 Oct 03 Oct 2.300 2.00 87 15 Oct 09:32 am Manoj Kumar Pande, Assistant Engineer Civil, PD Nainital
5 PD Nainital MDR 7847 नैनीताल बाईपास मोटर मार्ग [ Ch. 0.000 - 6.500] 6.500 3.000 2.00 01 Oct 03 Oct 3.000 4.75 158 13 Oct 15:43 pm Govind Singh Janoti, Assistant Engineer Civil, PD Nainital
6 PD Nainital ODR 427 पटुवाडागर पहुॅच मार्ग [ Ch. 0.000 - 3.000] 3.000 3.000 6.00 01 Oct 03 Oct 3.000 3.00 100 13 Oct 08:02 am Govind Singh Janoti, Assistant Engineer Civil, PD Nainital
7 PD Nainital ODR 430 एच0एम0टी0 कालौनी पहुॅच मार्ग [ Ch. 0.000 - 1.300] 1.300 1.300 6.00 01 Oct 03 Oct 1.300 1.30 100 13 Oct 08:02 am Govind Singh Janoti, Assistant Engineer Civil, PD Nainital