All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 3 144.75 26.00 44.00 01 Oct 2024 31 Oct 2024 26.00 26.00 100.00 %
MDR 3 85.03 22.00 40.00 01 Oct 2024 31 Oct 2024 22.00 22.00 100.00 %
6 229.78 48.00 84.00 48.00 48.00 100.00 %
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 CD Nainital SH 5529 रामनगर भण्डारपानी अमगड़ी बोहराकोट आखूलढूँगा तल्ली सेठी बेतालघाट रतौड़ा भुजान विशालकोट जैना रींची बिल्लेख राज्य मार्ग [ Ch. 44.250 - 68.735] 24.485 8.000 12.00 01 Oct 31 Oct 8.000 8.00 100 15 Oct 18:56 pm Govind Ballabh Joshi, Assistant Engineer Civil, CD Kapkot 5
2 CD Nainital SH 5462 गर्जिया (घुघुतियाधार) बेतालघाट खैेरना ढोकाना ओडाखान पसियापानी भटेलिया मुक्तेश्वर राज्य मार्ग [ Ch. 29.500 - 111.610] 82.110 6.000 12.00 01 Oct 31 Oct 6.000 6.00 100 14 Oct 17:43 pm Rajendra Giri, Assistant Engineer Civil, CD Lohaghat 1
3 CD Nainital SH 5494 खुटानी भवाली धानाचूली पतलोट रीठासाहिब मीनार धूनाघाट चम्पावत मंच तामली राज्य मार्ग [ Ch. 6.000 - 44.150] 38.150 12.000 20.00 01 Oct 31 Oct 12.000 12.00 100 16 Oct 09:11 am Prakash Chandra Pant, Assistant Engineer Civil, CD Nainital 2
4 CD Nainital MDR 477 रामगढ़ मल्ला डाक बंगला झूतिया मोटर मार्ग [ Ch. 0.000 - 11.530] 11.530 12.000 20.00 01 Oct 31 Oct 12.000 12.00 100 16 Oct 09:11 am Prakash Chandra Pant, Assistant Engineer Civil, CD Nainital 3
5 CD Nainital MDR 5686 लक्ष्मीखान तल्ला रामगढ नथुवाखान प्यूडा क्वारब मोटर मार्ग [ Ch. 0.000 - 41.730] 41.730 5.000 10.00 01 Oct 31 Oct 5.000 5.00 100 12 Oct 09:11 am Prakash Chandra Pant, Assistant Engineer Civil, CD Nainital 5
6 CD Nainital MDR 474 मौना ल्वेशाल कालापातल मोटर मार्ग [ Ch. 0.000 - 31.770] 31.770 5.000 10.00 01 Oct 31 Oct 5.000 5.00 100 12 Oct 09:12 am Prakash Chandra Pant, Assistant Engineer Civil, CD Nainital 6