All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 2 46.50 8.00 27.00 01 Oct 2024 22 Oct 2024 8.00 8.00 100.00 %
2 46.50 8.00 27.00 8.00 8.00 100.00 %
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 TD Berinaag SH 7872 अल्मोड़ा बेरीनाग अस्कोट राज्य मार्ग [ Ch. 105.000 - 125.000] 20.000 4.000 10.00 01 Oct 22 Oct 4.000 4.00 100 15 Oct 17:05 pm Kanta Prasad, Assistant Engineer Civil, TD Berinaag
2 TD Berinaag SH 5450 डगोली सैलानी दाडिमखेत हडबाड पन्द्रहपाली बालीघाट दोफाड धरमघर कोटमन्या पाखू थल सातसिलिग राज्य मार्ग [ Ch. 106.040 - 132.540] 26.500 4.000 17.00 01 Oct 22 Oct 4.000 4.00 100 14 Oct 19:50 pm Kanta Prasad, Additional Assistant Engineer Civil, TD Berinaag