Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 4 42.68 19.00 28.50 01 Oct 2024 31 Oct 2024 19.00 19.00 100.00 %
MDR 1 17.60 6.00 18.00 01 Oct 2024 23 Oct 2024 6.00 6.00 100.00 %
ODR 1 7.65 2.00 5.00 16 Sep 2024 20 Sep 2024 2.00 2.00 100.00 %
6 67.93 27.00 51.50 27.00 27.00 100.00 %
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 CD Khatima SH 6538 खटीमा मेलाघाट बनमहोलिया राज्य मार्ग [ Ch. 0.000 - 3.000] 3.000 5.000 9.50 10 Oct 30 Sep 5.000 5.00 100 25 Sep 16:57 pm Prem Prakash Tewari, Assistant Engineer Civil, CD Khatima
2 CD Khatima SH 7746 खटीमा मेलाघाट बनमहोलिया राज्य मार्ग [ Ch. 3.000 - 10.600] 7.600 0.000 0.00 01 Oct 04 Oct 0.000 - -
3 CD Khatima SH 7721 झनकट बिरिया श्रीपुर बिछुवा बिगराबाग चकरपुर कालापुल झनकईया मुडेली सत्रहमील नानकसागर राज्य मार्ग [ Ch. 22.200 - 40.280] 18.080 9.000 9.00 01 Oct 31 Oct 9.000 9.00 100 08 Oct 13:02 pm Prem Prakash Tewari, Assistant Engineer Civil, CD Khatima
4 CD Khatima SH 5589 पूरनपुर माधोटांडा राज्य मार्ग [ Ch. 0.000 - 14.000] 14.000 5.000 10.00 01 Oct 08 Oct 5.000 5.00 100 06 Oct 13:00 pm Prem Prakash Tewari, Assistant Engineer Civil, CD Khatima
5 CD Khatima MDR 6377 सिसईखेड़ा साधुनगर नलई मोटर मार्ग [ Ch. 0.000 - 17.600] 17.600 6.000 18.00 01 Oct 23 Oct 6.000 6.00 100 15 Oct 17:23 pm Himanshu Bhatt, Assistant Engineer Civil, CD Khatima 3
6 CD Khatima ODR 6380 खटीमा छिनकी बिरिया झनकट मार्ग [ Ch. 0.000 - 7.650] 7.650 2.000 5.00 16 Sep 20 Sep 2.000 2.00 100 18 Sep 13:06 pm Himanshu Bhatt, Assistant Engineer Civil, CD Khatima 3