All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 1 18.00 16.00 15.00 01 Oct 2024 12 Oct 2024 16.00 16.00 100.00 %
MDR 1 12.76 5.00 5.00 01 Oct 2024 05 Oct 2024 5.00 5.00 100.00 %
ODR 1 10.00 8.00 8.00 01 Oct 2024 07 Oct 2024 8.00 8.00 100.00 %
3 40.76 29.00 28.00 29.00 29.00 100.00 %
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 PD Bhatwari SH 5562 उत्तरकाशी घनसाली तिलवाडा राज्य मार्ग [ Ch. 0.000 - 18.000] 18.000 16.000 15.00 01 Oct 12 Oct 16.000 16.00 100 14 Oct 18:27 pm Andeep Rana, Executive Engineer Civil, PD Didihaat 5
2 PD Bhatwari MDR 5652 तेखला महिडाण्डा मोटर मार्ग [ Ch. 0.000 - 12.760] 12.760 5.000 5.00 01 Oct 05 Oct 5.000 5.00 100 07 Oct 17:08 pm Dharamveer Singh, Assistant Engineer Civil, PD Bhatwari 5
3 PD Bhatwari ODR 1915 भटवाड़ी बार्सू मोटर मार्ग [ Ch. 0.000 - 10.000] 10.000 8.000 8.00 01 Oct 07 Oct 8.000 8.00 100 09 Oct 13:13 pm Dharamveer Singh, Assistant Engineer Civil, PD Bhatwari