All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
MDR 2 65.19 23.50 56.00 01 Oct 2024 31 Oct 2024 23.50 23.50 100.00 %
ODR 1 1.20 0.20 0.75 01 Oct 2024 03 Oct 2024 0.20 0.20 100.00 %
3 66.39 23.70 56.75 23.70 23.70 100.00 %
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 PD Karnprayag MDR 2128 नन्दप्रयाग-घाट घाट सुतोल कनोल मोटर मार्ग [ Ch. 0.000 - 48.690] 48.690 21.000 48.00 01 Oct 31 Oct 21.000 21.00 100 17 Oct 16:41 pm Gyanendra Kumar, Assistant Engineer Civil, PD Gopeshwar 6
2 PD Karnprayag MDR 5665 घाट रामणी मोटर मार्ग [ Ch. 0.000 - 16.500] 16.500 2.500 8.00 01 Oct 15 Oct 2.500 2.50 100 13 Oct 15:09 pm Sansar Singh, Assistant Engineer Civil, CD Pauri
3 PD Karnprayag ODR 2130 पंचपुलिया से आन्तरिक मार्ग [ Ch. 0.000 - 1.200] 1.200 0.200 0.75 01 Oct 03 Oct 0.200 0.20 100 09 Oct 15:39 pm Navin Lal Verma, Executive Engineer Civil, PD Karnprayag 1