Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 4 155.03 87.00 93.00 01 Oct 2024 31 Oct 2024 87.00 97.00 111.49 %
MDR 1 16.00 3.00 5.00 01 Oct 2024 06 Oct 2024 3.00 3.00 100.00 %
5 171.03 90.00 98.00 90.00 100.00 111.11 %
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 TD Gaucher SH 5476 कर्णप्रयाग नौटी पैठाणी राज्य मार्ग [ Ch. 0.000 - 47.150] 47.150 42.000 35.00 01 Oct 31 Oct 42.000 42.00 100 17 Oct 17:46 pm Anup Singh, Assistant Engineer Civil, CD Gaucher 3
2 TD Gaucher SH 5622 आदिबद्री नौटी राज्य मार्ग [ Ch. 0.000 - 38.530] 38.530 25.000 25.00 01 Oct 25 Oct 25.000 25.00 100 17 Oct 17:41 pm Rajesh Kumar, Assistant Engineer Civil, CD Gaucher
3 TD Gaucher SH 2186 कर्णप्रयाग धारदुंगी मैखूरा कंडारा सोनला राज्य मार्ग [ Ch. 0.000 - 44.850] 44.850 7.000 15.00 01 Oct 08 Oct 7.000 7.00 100 17 Oct 17:38 pm Mohammad Rashid, Assistant Engineer Civil, CD Gaucher
4 TD Gaucher SH 5626 गौचर सिदोली राज्य मार्ग [ Ch. 0.000 - 24.500] 24.500 13.000 18.00 01 Oct 20 Oct 13.000 23.00 177 09 Oct 16:18 pm Anup Singh, Assistant Engineer Civil, CD Gaucher 18
5 TD Gaucher MDR 5625 कर्णप्रयाग नैनीसैंण मोटर मार्ग [ Ch. 0.000 - 16.000] 16.000 3.000 5.00 01 Oct 06 Oct 3.000 3.00 100 15 Oct 17:09 pm Mohammad Rashid, Assistant Engineer Civil, CD Gaucher