Division | Type | ID | Name | Total Length | Target Length | Amount | Planned Start | Planned End | Till Date Target | Progress | % | Progress On | Progress By | Images | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | CD Narendnagar | SH | 5518 | पौड़ी देवप्रयाग गजा जाजल राज्य मार्ग [ Ch. 49.000 - 119.500] | 70.500 | 6.000 | 15.00 | 01 Oct | 11 Oct | 6.000 | 6.00 | 100 | 08 Oct 17:04 pm | Manoj Singh Panwar, Assistant Engineer Civil, Engineer-in-Chief Office | 5 |