Back

Office :

All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 1 41.20 9.00 22.50 01 Oct 2024 30 Oct 2024 9.00 9.00 100.00 %
MDR 2 81.50 7.00 17.50 01 Oct 2024 14 Oct 2024 7.00 7.00 100.00 %
3 122.70 16.00 40.00 16.00 16.00 100.00 %
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 TD Thathyd SH 5435 बड़ेथी बनचौरा बद्रीगाड राज्य मार्ग [ Ch. 53.400 - 94.600] 41.200 9.000 22.50 01 Oct 30 Oct 9.000 9.00 100 15 Oct 14:05 pm Madan Mohan Joshi, Assistant Engineer Civil, TD Thatyur 18
2 TD Thathyd MDR 5653 अगलाड थत्यूड अलमस बैन्ड मोटर मार्ग [ Ch. 0.000 - 50.500] 50.500 2.000 5.00 05 Oct 11 Oct 2.000 2.00 100 12 Oct 15:12 pm Prashant Bhatt, Assistant Engineer Civil, TD Thatyur 2
3 TD Thathyd MDR 5655 नैनबाग घोडाखुरी ऐन्दी मोटर मार्ग [ Ch. 0.000 - 31.000] 31.000 5.000 12.50 01 Oct 14 Oct 5.000 5.00 100 09 Oct 16:33 pm Madan Mohan Joshi, Assistant Engineer Civil, TD Thatyur 7