All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 1 49.00 20.00 14.00 01 Oct 2024 15 Oct 2024 20.00 20.00 100.00 %
ODR 1 3.50 3.50 5.00 01 Oct 2024 04 Oct 2024 3.50 3.50 100.00 %
2 52.50 23.50 19.00 23.50 23.50 100.00 %
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 PD Pauri SH 5519 पौड़ी देवप्रयाग गजा जाजल राज्य मार्ग [ Ch. 0.000 - 49.000] 49.000 20.000 14.00 01 Oct 15 Oct 20.000 20.00 100 13 Oct 08:58 am Madhavi Kanojiya, Assistant Engineer Civil, PD Pauri 9