All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
MDR 4 85.00 37.00 53.00 01 Oct 2024 22 Oct 2024 37.00 37.00 100.00 %
4 85.00 37.00 53.00 37.00 37.00 100.00 %
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 CD Pauri MDR 5664 चौबट्टाखाल गवाणी पोखडा मोटर मार्ग [ Ch. 0.000 - 31.500] 31.500 21.000 28.00 01 Oct 22 Oct 21.000 21.00 100 14 Oct 14:45 pm Ravi Kumar, Assistant Engineer Civil, CD Pauri 9
2 CD Pauri MDR 4523 सूंगरखाल सीकूखाल ज्वाल्पादेवी मोटर मार्ग [ Ch. 0.000 - 31.000] 31.000 5.000 7.00 01 Oct 05 Oct 5.000 5.00 100 15 Oct 11:50 am Sansar Singh, Assistant Engineer Civil, CD Pauri
3 CD Pauri MDR 4550 बीजोरापानी कुंजखाल कोलाखाल पंडियाना बसडांग जयकोट मोटर मार्ग [ Ch. 0.000 - 7.250] 7.250 5.000 18.00 01 Oct 18 Oct 5.000 5.50 110 10 Oct 13:09 pm Kishor Kumar, Assistant Engineer Civil, CD Pauri
4 CD Pauri MDR 7505 बीजोरापानी कुंजखाल कोलाखाल पंडियाना बसडांग जयकोट मोटर मार्ग [ Ch. 8.750 - 24.000] 15.250 6.000 0.00 01 Oct 18 Oct 6.000 5.50 92 12 Oct 11:37 am Sansar Singh, Assistant Engineer Civil, CD Pauri