All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 1 155.10 11.00 22.00 01 Oct 2024 25 Oct 2024 11.00 11.00 100.00 %
MDR 1 92.00 13.00 26.00 01 Oct 2024 25 Oct 2024 13.00 13.00 100.00 %
2 247.10 24.00 48.00 24.00 24.00 100.00 %
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 PD Lansdown SH 5591 शहीद संदीप सिंह रावत राज्य मार्ग (घटटूगाड सिलोगी गुमखाल लैंसडौन डेरियाखाल रिखणीखाल बीरौंखाल मोटर मार्ग ) [ Ch. 14.500 - 169.600] 155.100 11.000 22.00 01 Oct 25 Oct 11.000 11.00 100 14 Oct 16:25 pm Vivek Kumar Singh, Executive Engineer Civil, PD Lansdown
2 PD Lansdown MDR 4661 सतपुली दुधारखाल धारकोट सिसल्डी मोटर मार्ग [ Ch. 0.000 - 92.000] 92.000 13.000 26.00 01 Oct 25 Oct 13.000 13.00 100 15 Oct 13:13 pm Vivek Kumar Singh, Executive Engineer Civil, PD Lansdown