All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
MDR 1 21.80 3.00 6.00 01 Apr 2025 30 Apr 2025 3.00 3.00 100.00 %
ODR 1 8.00 5.00 7.00 01 Apr 2025 30 Apr 2025 5.00 5.00 100.00 %
2 29.80 8.00 13.00 8.00 8.00 100.00 %
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 CD Kapkot MDR 5609 कपकोट कर्मी मोटर मार्ग [ Ch. 0.000 - 21.800] 21.800 3.000 6.00 01 Apr 30 Apr 3.000 3.00 100 05 May 12:31 pm Ankur Singh, Assistant Engineer Civil, CD Kapkot 7
2 CD Kapkot ODR 5763 बैड़ा पाखड़ ओखलधार से दोफाड़ मोटर मार्ग [ Ch. 8.000 - 16.000] 8.000 5.000 7.00 01 Apr 30 Apr 5.000 5.00 100 05 May 12:32 pm Ankur Singh, Assistant Engineer Civil, CD Kapkot 14