All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 2 50.85 6.00 13.00 01 Apr 2025 30 Apr 2025 6.00 6.00 100.00 %
MDR 1 27.03 10.00 20.00 01 Apr 2025 30 Apr 2025 10.00 10.00 100.00 %
ODR 1 2.36 2.36 10.00 01 Apr 2025 30 Apr 2025 2.36 2.36 100.00 %
4 80.24 18.36 43.00 18.36 18.36 100.00 %
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 CD Askote SH 5516 ओगला से भागीचैरा पस्मा हंसेश्वर राज्य मार्ग [ Ch. 0.000 - 23.700] 23.700 2.000 5.00 01 Apr 30 Apr 2.000 2.00 100 15 May 11:40 am Jagat Singh Bora, Assistant Engineer Civil, CD Askote
2 CD Askote SH 5456 देवलथल कनालीछीना से न्वाली पीपली द्वालीसेरा राज्य मार्ग [ Ch. 0.000 - 27.150] 27.150 4.000 8.00 01 Apr 30 Apr 4.000 4.00 100 15 May 11:42 am Jagat Singh Bora, Assistant Engineer Civil, CD Askote
3 CD Askote MDR 5692 तवाघाट नारायण आश्रम मोटर मार्ग [ Ch. 0.000 - 27.025] 27.025 10.000 20.00 01 Apr 30 Apr 10.000 10.00 100 15 May 11:40 am Ashish Lunthi, Assistant Engineer Civil, Engineer-in-Chief Office
4 CD Askote ODR 1024 आन्तरिक मार्ग धारचूला [ Ch. 0.000 - 2.360] 2.360 2.360 10.00 01 Apr 30 Apr 2.360 2.36 100 15 May 11:41 am Ashish Lunthi, Assistant Engineer Civil, Engineer-in-Chief Office