All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
ODR 1 14.60 6.00 9.00 01 Apr 2025 30 Apr 2025 0.33 0.00 0.00 %
SH 1 41.80 54.40 55.00 01 Apr 2025 30 Apr 2025 2.97 0.00 0.00 %
MDR 1 18.00 12.00 20.00 01 Apr 2025 30 Apr 2025 0.66 0.00 0.00 %
3 74.40 72.40 84.00 3.96 0.00 0.00 %
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 CD Lohaghat ODR 6001 किमतोली पुल्ला चमदेवल जाख निडिल मोटर मार्ग [ Ch. 0.000 - 14.600] 14.600 6.000 9.00 01 Apr 30 Apr 0.330 - -
2 CD Lohaghat SH 5569 काठगोदाम (रानीबाग) भीमताल खुटानी चांफी पदमपुरी धानाचूली पहाड़पानी शहरफाटक मौरनौला देवीधुरा लोहाघाट पंचेश्वर राज्य मार्ग [ Ch. 147.000 - 188.800] 41.800 54.400 55.00 01 Apr 30 Apr 2.970 - -
3 CD Lohaghat MDR 5684 किमतोली रौशाल मोटर मार्ग [ Ch. 0.000 - 18.000] 18.000 12.000 20.00 01 Apr 30 Apr 0.660 - -