All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 1 24.23 8.60 18.58 01 Apr 2025 30 Jun 2025 0.00 0.00
MDR 1 7.60 7.60 16.42 01 Apr 2025 30 Jun 2025 0.00 0.00
2 31.83 16.20 35.00 0.00 0.00
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 CD Haldwani SH 7900 रामनगर कालाढॅूगी हल्द्वानी काठगोदाम चोरगलिया सितारगंज बिल्टी राज्य मार्ग [ Ch. 28.370 - 52.600] 24.230 8.600 18.58 01 Apr 30 Jun 0.000 - -
2 CD Haldwani MDR 5597 कुसुमखेड़ा लामाचौड़ मोटर मार्ग [ Ch. 0.000 - 7.600] 7.600 7.600 16.42 01 Apr 30 Jun 0.000 - -