Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 1 24.23 8.60 18.58 01 Apr 2025 30 Jun 2025 8.59 8.60 100.12 %
MDR 1 7.60 7.60 16.42 01 Apr 2025 30 Jun 2025 7.59 7.60 100.13 %
2 31.83 16.20 35.00 16.18 16.20 100.12 %
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 CD Haldwani SH 7900 रामनगर कालाढॅूगी हल्द्वानी काठगोदाम चोरगलिया सितारगंज बिल्टी राज्य मार्ग [ Ch. 28.370 - 52.600] 24.230 8.600 18.58 01 Apr 30 Jun 8.590 8.60 100 13 May 07:40 am Lalit Tiwari, Assistant Engineer Civil, CD Haldwani