Back

Office :

All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
MDR 2 65.19 18.00 30.00 01 Apr 2025 30 Apr 2025 18.00 18.00 100.00 %
ODR 2 11.77 4.00 5.50 01 Apr 2025 30 Apr 2025 4.00 4.00 100.00 %
4 76.96 22.00 35.50 22.00 22.00 100.00 %
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 PD Karnprayag MDR 2128 नन्दप्रयाग-घाट घाट सुतोल कनोल मोटर मार्ग [ Ch. 0.000 - 48.690] 48.690 17.000 28.00 01 Apr 30 Apr 17.000 17.00 100 05 May 12:49 pm Gyanendra Kumar, Assistant Engineer Civil, PD Karnprayag 12
2 PD Karnprayag ODR 2130 पंचपुलिया से आन्तरिक मार्ग [ Ch. 0.000 - 1.200] 1.200 1.000 1.50 01 Apr 30 Apr 1.000 1.20 120 26 Apr 13:43 pm Dinesh Giriraj, Assistant Engineer Civil, PD Karnprayag 2
3 PD Karnprayag ODR 2132 सेमा बैराऊ मोटर मार्ग (थिरपाक काण्डई बैरासकुण्ड मोटर मार्ग) [ Ch. 0.000 - 10.570] 10.570 3.000 4.00 01 Apr 30 Apr 3.000 2.80 93 15 May 10:47 am Yogesh Chandra Pant, Assistant Engineer Civil, PD Karnprayag
4 PD Karnprayag MDR 5665 घाट रामणी मोटर मार्ग [ Ch. 0.000 - 16.500] 16.500 1.000 2.00 01 Apr 30 Apr 1.000 1.00 100 05 May 12:52 pm Gyanendra Kumar, Assistant Engineer Civil, PD Karnprayag