All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
MDR 2 81.50 22.00 40.00 01 Apr 2025 30 Apr 2025 22.00 22.00 100.00 %
SH 1 41.20 24.60 61.50 01 Apr 2025 30 Jun 2025 24.58 24.60 100.08 %
3 122.70 46.60 101.50 46.58 46.60 100.04 %
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 TD Thathyd MDR 5653 अगलाड थत्यूड अलमस बैन्ड मोटर मार्ग [ Ch. 0.000 - 50.500] 50.500 14.000 20.00 01 Apr 30 Apr 14.000 14.00 100 30 Apr 15:45 pm Prashant Bhatt, Assistant Engineer Civil, TD Thatyur 9
2 TD Thathyd MDR 5655 नैनबाग घोडाखुरी ऐन्दी मोटर मार्ग [ Ch. 0.000 - 31.000] 31.000 8.000 20.00 01 Apr 30 Apr 8.000 8.00 100 30 Apr 14:43 pm Madan Mohan Joshi, Assistant Engineer Civil, TD Thatyur 27
3 TD Thathyd SH 5435 बड़ेथी बनचौरा बद्रीगाड राज्य मार्ग [ Ch. 53.400 - 94.600] 41.200 24.600 61.50 01 Apr 30 Jun 24.580 24.60 100 02 May 15:10 pm Madan Mohan Joshi, Assistant Engineer Civil, TD Thatyur 55