All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 3 56.00 19.00 40.00 01 Apr 2025 30 Apr 2025 1.04 5.00 480.77 %
MDR 3 23.10 13.00 21.00 01 Apr 2025 30 Apr 2025 0.71 0.00 0.00 %
ODR 3 17.00 15.00 28.00 01 Apr 2025 30 Apr 2025 0.82 4.00 487.80 %
9 96.10 47.00 89.00 2.57 9.00 350.19 %
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 PD Haridwar SH 5517 पुराना दिल्ली नीतिपास राज्य मार्ग [ Ch. 0.000 - 11.420] 11.420 10.000 15.00 01 Apr 30 Apr 0.550 - - 15
2 PD Haridwar SH 5473 ज्वालापुर सराय एक्कड़ बहादरपुर जट अम्बूवाला धनपुरा राज्य मार्ग [ Ch. 0.000 - 11.240] 11.240 4.000 10.00 01 Apr 30 Apr 0.220 - - 1
3 PD Haridwar SH 5539 रोशनाबाद कुडकावाला बिहारीगढ राज्य मार्ग [ Ch. 0.000 - 33.335] 33.335 5.000 15.00 01 Apr 30 Apr 0.270 5.00 1852 03 Apr 17:33 pm Satish Kumar, Assistant Engineer Civil, PD Haridwar 1
4 PD Haridwar MDR 5604 सीतापुर जमालपुर कलां जियापोता मोटर मार्ग [ Ch. 0.000 - 5.500] 5.500 5.000 5.00 01 Apr 30 Apr 0.270 - -
5 PD Haridwar MDR 5603 बढेड़ी राजपुताना अलावलपुर मोटर मार्ग [ Ch. 7.500 - 12.000] 4.500 4.000 8.00 01 Apr 30 Apr 0.220 - - 5
6 PD Haridwar MDR 5600 पिरान कलियर सोहलपुर मुजाहिदपुर सत्तीवाला कुड़कावाला मोटर मार्ग [ Ch. 6.000 - 19.100] 13.100 4.000 8.00 01 Apr 30 Apr 0.220 - - 1
7 PD Haridwar ODR 3969 राष्ट्रीय मार्ग संख्या 58 से औद्योगिक क्षेत्र तक चार लेन मार्ग [ Ch. 0.000 - 4.000] 4.000 4.000 8.00 01 Apr 30 Apr 0.220 4.00 1818 05 Apr 20:31 pm Kirti Vardhan Negi, Assistant Engineer Civil, PD Haridwar
8 PD Haridwar ODR 4067 रा० मा० -74 रसियाबगढ़ से पीली पड़ाव मोटर मार्ग [ Ch. 0.000 - 6.000] 6.000 4.000 12.00 01 Apr 30 Apr 0.220 - -
9 PD Haridwar ODR 3946 ज्वालापुर-ललताराव-चण्डीघाट मार्ग [ Ch. 0.000 - 7.000] 7.000 7.000 8.00 01 Apr 30 Apr 0.380 - -