All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 1 52.32 7.00 10.00 01 Apr 2025 30 Apr 2025 0.38 0.00 0.00 %
MDR 1 16.00 7.00 12.00 01 Apr 2025 30 Apr 2025 0.38 0.00 0.00 %
ODR 3 16.55 16.20 19.00 01 Apr 2025 30 Apr 2025 0.89 0.00 0.00 %
5 84.87 30.20 41.00 1.65 0.00 0.00 %
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 CD Pokhari SH 7838 रुद्रप्रयाग पोखरी गोपेश्वर राज्य मार्ग [ Ch. 35.000 - 87.320] 52.320 7.000 10.00 01 Apr 30 Apr 0.380 - - 4
2 CD Pokhari MDR 5086 पोखरी विशालखाल आली कांडई मोटर मार्ग [ Ch. 0.000 - 16.000] 16.000 7.000 12.00 01 Apr 30 Apr 0.380 - - 3
3 CD Pokhari ODR 5099 पोखरी हरिशंकर मोटर मार्ग [ Ch. 0.000 - 9.350] 9.350 9.000 10.00 01 Apr 30 Apr 0.490 - -
4 CD Pokhari ODR 5085 पोखरी बाजार लिंक मोटर मार्ग [ Ch. 0.000 - 0.500] 0.500 0.500 1.00 01 Apr 30 Apr 0.030 - -
5 CD Pokhari ODR 5083 जौरासी हापला कलसीर धोतीधार मोटर मार्ग [ Ch. 0.000 - 6.700] 6.700 6.700 8.00 01 Apr 30 Apr 0.370 - -