Back

Office :

All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
NH 4 229.20 66.00 25.00 01 Apr 2025 31 May 2025 65.60 0.00 0.00 %
4 229.20 66.00 25.00 65.60 0.00 0.00 %
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 NH Rudraprayag NH 5714 रुद्रप्रयाग गोरीकुंड राष्ट्रीय राजमार्ग [ Ch. 0.000 - 76.000] 76.000 21.000 7.00 01 Apr 31 May 20.870 - -
2 NH Rudraprayag NH 5727 गोपेश्वर ऊखीमठ बरमवारी राष्ट्रीय राजमार्ग [ Ch. 0.000 - 84.200] 84.200 32.000 10.00 01 Apr 31 May 31.810 - -
3 NH Rudraprayag NH 5721 ज्योलीकोट अल्मोड़ा कर्णप्रयाग राष्ट्रीय राजमार्ग [ Ch. 171.000 - 235.000] 64.000 10.000 6.00 01 Apr 31 May 9.940 - -
4 NH Rudraprayag NH 8683 दिल्ली गाजियाबाद बद्रीनाथ माणा राष्ट्रीय राजमार्ग [ Ch. 350.000 - 355.000] 5.000 3.000 2.00 01 Apr 31 May 2.980 - -