All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
MDR 3 55.61 8.56 129.07 01 Apr 2025 31 Mar 2026 0.00 3.50
VR 22 95.15 43.82 643.60 01 Apr 2025 31 Mar 2026 0.00 20.47
SH 5 140.30 37.02 595.50 01 Apr 2025 31 Mar 2026 0.00 3.70
30 291.06 89.40 1,368.17 0.00 27.67
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 PD Pithoragarh MDR 5690 ऐचोली जाख पुरान मेलडुगरी मोटर मार्ग [ Ch. 0.000 - 15.000] 15.000 2.140 34.82 01 Apr 31 Mar 0.000 - -
2 PD Pithoragarh MDR 5687 पिथौरागढ़ चण्डाक बांस आंवलाघाट मोटर मार्ग [ Ch. 0.000 - 30.610] 30.610 0.000 0.00 01 Apr 31 Mar 0.000 - -
3 PD Pithoragarh VR 6293 सातसिलिंग नाघर भुलगाॅव मोटर मार्ग [ Ch. 0.000 - 6.500] 6.500 1.610 23.67 01 Apr 31 Mar 0.000 1.30 - 28 May 13:18 pm Gopal Giri Goswami-AE
4 PD Pithoragarh VR 6226 जाख मेलडंगरी से पटवारी चैकी से पुरान प्राइमरी पाठशाला मोटर मार्ग। [ Ch. 0.000 - 1.000] 1.000 1.070 15.73 01 Apr 31 Mar 0.000 - -
5 PD Pithoragarh VR 6272 जाख मसाडी मोटर मार्ग [ Ch. 0.000 - 4.000] 4.000 5.350 78.58 01 Apr 31 Mar 0.000 - -
6 PD Pithoragarh VR 6228 बडारी से कांटे बोरा होते हेतु बौनकोट । [ Ch. 0.000 - 7.000] 7.000 2.140 31.42 01 Apr 31 Mar 0.000 - -
7 PD Pithoragarh VR 7835 देवलथल कनालीछीना मोटर मार्ग से बिसोनाखाल मोटर मार्ग [ Ch. 0.000 - 2.000] 2.000 0.750 11.01 01 Apr 31 Mar 0.000 0.70 - 28 May 13:18 pm Gopal Giri Goswami-AE
8 PD Pithoragarh VR 6292 सातसिलिग थल मोटर मार्ग के किमी0 10 से पैकटिया तक मोटर मार्ग [ Ch. 0.000 - 2.000] 2.000 2.140 31.46 01 Apr 31 Mar 0.000 - -
9 PD Didihaat SH 5426 अल्मोड़ा बेरीनाग अस्कोट राज्य मार्ग [ Ch. 125.000 - 159.000] 34.000 7.490 121.86 01 Apr 31 Mar 0.000 - -
10 PD Didihaat SH 5428 अल्मोेड़ा बेरीनाग थल मुवानी चैबाटी सानदेव डीडीहाट ओगला राज्य मार्ग [ Ch. 0.000 - 19.500] 19.500 5.350 87.04 01 Apr 31 Mar 0.000 - -
11 TD Berinaag SH 5425 अल्मोड़ा बेरीनाग अस्कोट राज्य मार्ग [ Ch. 61.325 - 90.000] 28.675 13.750 223.71 01 Apr 31 Mar 0.000 - - 07 Apr 15:56 pm SANGITA DHANIK-Junior Engineer Technical 1
12 TD Berinaag SH 7872 अल्मोड़ा बेरीनाग अस्कोट राज्य मार्ग [ Ch. 105.000 - 125.000] 20.000 6.150 100.06 01 Apr 31 Mar 0.000 - - 07 Apr 15:56 pm SANGITA DHANIK-Junior Engineer Technical
13 TD Berinaag MDR 5758 दशाईथल खिरमाण्डे नैनी सेराघाट मोटर मार्ग [ Ch. 33.000 - 43.000] 10.000 6.420 94.25 01 Apr 31 Mar 0.000 3.50 - 18 Jun 15:00 pm SANGITA DHANIK-Junior Engineer Technical 2
14 CD Askote VR 1053 शहीद सिपाही होशियार सिंह मोटर मार्ग [ Ch. 0.000 - 12.400] 12.400 7.140 104.81 01 Apr 31 Mar 0.000 0.70 - 16 May 15:53 pm Manoj Singh Panwar-AE
15 CD Askote VR 1033 बन्दरलीमा आणागांव मोटर मार्ग [ Ch. 0.000 - 4.900] 4.900 2.030 29.80 01 Apr 31 Mar 0.000 2.03 - 02 Jun 23:22 pm Dheeraj Tiwari-JE T
16 PD Champawat VR 1067 नरसिंहडॉडा गुरौली मोटर मार्ग [ Ch. 0.000 - 8.000] 8.000 4.280 62.83 01 Apr 31 Mar 0.000 4.28 - 14 May 21:14 pm Neeraj Joshi-Junior Engineer Technical
17 CD Lohaghat SH 5999 लोहाघाट बाराकोट सिमलखेत काफलीखान भनोली राज्य मार्ग [ Ch. 0.000 - 38.120] 38.120 4.280 62.83 01 Apr 31 Mar 0.000 3.70 - 16 Jun 22:20 pm Pallavi Chaudhary-Junior Engineer Technical
18 CD Lohaghat VR 6006 लोहाघाट चैमेल मोटर मार्ग [ Ch. 0.000 - 7.500] 7.500 3.210 47.19 01 Apr 31 Mar 0.000 1.00 - 16 Jun 22:20 pm Pallavi Chaudhary-Junior Engineer Technical
19 Other VR 6024 .....मोटर मार्ग [ Ch. 0.000 - 0.100] 0.100 1.070 15.71 01 Apr 31 Mar 0.000 1.07 - 06 Jun 22:07 pm Pallavi Chaudhary-Junior Engineer Technical
20 CD Lohaghat VR 6068 पाटी जौलमेल से अस्पताल तक मोटर मार्ग [ Ch. 0.000 - 1.500] 1.500 0.540 7.94 01 Apr 31 Mar 0.000 0.54 - 19 May 20:11 pm Pallavi Chaudhary-Junior Engineer Technical
21 CD Lohaghat VR 6082 लोहाघाट पंचेश्वर मोटर मार्ग के गंगनौला से अ०जा० बस्ती बचकड़िया तक मोटर मार्ग [ Ch. 0.000 - 2.450] 2.450 0.000 0.00 01 Apr 31 Mar 0.000 - -
22 CD Lohaghat VR 6028 गर्सलेख गरसाड़ी मोटर मार्ग [ Ch. 0.000 - 6.000] 6.000 2.680 39.34 01 Apr 31 Mar 0.000 2.68 - 18 Jun 22:07 pm Pallavi Chaudhary-Junior Engineer Technical
23 CD Lohaghat VR 6007 पाटी बाजार मोटर मार्ग [ Ch. 0.000 - 0.750] 0.750 0.000 0.00 01 Apr 31 Mar 0.000 - -
24 CD Lohaghat VR 6023 टनकपुर पिथौरागढ़ मोटर मार्ग से बलाई तक मोटर मार्ग [ Ch. 0.000 - 3.000] 3.000 2.140 31.42 01 Apr 31 Mar 0.000 2.14 - 06 Jun 22:04 pm Pallavi Chaudhary-Junior Engineer Technical
25 CD Lohaghat VR 6020 अश्वाताल झलानदेव मल्ला थुवमाहरा ढेरना मंदिर तक मोटर मार्ग [ Ch. 0.000 - 6.500] 6.500 1.070 15.71 01 Apr 31 Mar 0.000 1.07 - 18 Jun 22:01 pm Pallavi Chaudhary-Junior Engineer Technical
26 CD Lohaghat VR 6058 पाटी तहसील मोटर मार्ग [ Ch. 0.000 - 0.500] 0.500 0.540 7.94 01 Apr 31 Mar 0.000 0.54 - 19 May 20:28 pm Pallavi Chaudhary-Junior Engineer Technical
27 CD Lohaghat VR 6060 किमतोली रौशाल मोटर मार्ग से अश्लाड़ मोटर मार्ग [ Ch. 0.000 - 5.000] 5.000 0.700 10.29 01 Apr 31 Mar 0.000 - -
28 CD Lohaghat VR 6095 लमताल से खर्क मोटर मार्ग [ Ch. 0.000 - 3.000] 3.000 1.070 15.73 01 Apr 31 Mar 0.000 - -
29 PD Champawat VR 1170 रीठा बिनवालगॉंव मोटर मार्ग [ Ch. 0.000 - 5.000] 5.000 2.420 35.57 01 Apr 31 Mar 0.000 2.42 - 14 May 21:15 pm Neeraj Joshi-Junior Engineer Technical
30 CD Lohaghat VR 6080 बर्दाखान-पठलती-देवराड़ी (बिसराड़ी)-आली-पट्यूड़ा मोटर मार्ग। [ Ch. 0.000 - 6.050] 6.050 1.870 27.45 16 Jun 31 Mar 0.000 - -