All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 10 653.12 116.36 1,854.37 01 Apr 2025 31 Mar 2026 0.00 31.93
VR 16 127.89 46.77 695.72 01 Apr 2025 31 Mar 2026 0.00 35.86
MDR 6 184.63 33.17 520.97 01 Apr 2025 31 Mar 2026 0.00 17.12
ODR 1 1.65 1.77 28.80 01 Apr 2025 31 Mar 2026 0.00 1.77
33 967.29 198.07 3,099.86 0.00 86.68
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 PD Pauri SH 5519 पौड़ी देवप्रयाग गजा जाजल राज्य मार्ग [ Ch. 0.000 - 49.000] 49.000 7.850 127.72 01 Apr 31 Mar 0.000 7.85 - 09 May 16:46 pm Mr Devpal Singh Rawat-Junior Engineer Technical 15
2 PD Pauri VR 4413 पौडी देवप्रयाग मोटर मार्ग से सूनर गदेरा सल्डा मार्ग [ Ch. 0.000 - 2.640] 2.640 2.830 41.60 01 Apr 31 Mar 0.000 2.00 - 18 Jun 18:57 pm madhavi kanojia-AE
3 PD Pauri VR 4466 बडोली बैण्ड से मन्दिर तक मोटर मार्ग [ Ch. 0.000 - 0.400] 0.400 0.430 6.32 01 Apr 31 Mar 0.000 - -
4 PD Pauri VR 4475 घोडीखाल गोदी गदना भिमली आलधार मोटर मार्ग [ Ch. 0.000 - 6.250] 6.250 1.610 23.67 01 Apr 31 Mar 0.000 - -
5 PD Pauri VR 4490 रामकुण्ड में पौडी देवप्रयाग मोटर मार्ग से देवप्रयाग इण्टर कालेज से खेडा तक मोटर मार्ग [ Ch. 0.000 - 0.650] 0.650 0.700 10.29 01 Apr 31 Mar 0.000 - -
6 CD Pauri VR 8582 पोखर खुर्कताल मोटर मार्ग [ Ch. 0.000 - 21.070] 21.070 5.350 78.54 01 Apr 31 Mar 0.000 5.35 - 11 Jun 15:21 pm Mr Vikash Bisht-Junior Engineer Technical
7 CD Pauri VR 8579 सीकू कणडेरी मोटर मोटर मार्ग [ Ch. 0.000 - 9.000] 9.000 6.420 94.25 01 Apr 31 Mar 0.000 3.90 - 11 Jun 15:21 pm Mr Vikash Bisht-Junior Engineer Technical
8 CD Pauri VR 4565 चौबट्टाखाल दांथा मोटर मार्ग [ Ch. 0.000 - 7.350] 7.350 6.420 94.34 01 Apr 31 Mar 0.000 4.28 - 11 Jun 15:21 pm Mr Vikash Bisht-Junior Engineer Technical
9 CD Pauri VR 4596 असनोली ओणी खण्डाह मोटर मार्ग [ Ch. 0.000 - 5.000] 5.000 2.140 31.42 01 Apr 31 Mar 0.000 2.14 - 01 May 16:16 pm Mr Vikash Bisht-Junior Engineer Technical
10 CD Pauri VR 4556 शहीद नेत्र सिंह मोटर मार्ग (तैला बारे मोटर मार्ग) [ Ch. 0.000 - 5.000] 5.000 2.140 31.42 01 Apr 31 Mar 0.000 2.14 - 23 Apr 17:55 pm Mr Vikash Bisht-Junior Engineer Technical
11 CD Srinagar SH 5488 पौड़ी खिर्सू खेडाखाल खांखरा राज्य मार्ग [ Ch. 0.000 - 32.220] 32.220 21.730 326.66 01 Apr 31 Mar 0.000 - -
12 CD Srinagar VR 4618 डबरूखाल मोलखाखाल टीला मोटर मार्ग [ Ch. 0.000 - 19.025] 19.025 4.280 62.83 01 Apr 31 Mar 0.000 4.28 - 02 Jun 19:28 pm Veer Singh-JET
13 CD Srinagar VR 4612 रामपुर गवाणा मोटर मार्ग [ Ch. 0.000 - 4.000] 4.000 1.070 16.05 01 Apr 31 Mar 0.000 1.07 - 01 May 15:54 pm Veer Singh-JET 7
14 PD Lansdown SH 5591 शहीद संदीप सिंह रावत राज्य मार्ग (घटटूगाड सिलोगी गुमखाल लैंसडौन डेरियाखाल रिखणीखाल बीरौंखाल मोटर मार्ग ) [ Ch. 14.500 - 169.600] 155.100 2.680 43.60 01 Apr 31 Mar 0.000 2.68 - 05 Jun 22:52 pm Mr Sachin Kumar-Junior Engineer Technical 1
15 PD Lansdown SH 5502 स्व0 जगमोहन सिंह नेगी (लक्ष्मणझूला दुगड्डा रथुवाढाब धुमाकोट ) राज्य मार्ग [ Ch. 189.000 - 216.500] 27.500 9.630 156.68 01 Apr 31 Mar 0.000 9.63 - 16 Jun 15:28 pm Mr Sachin Kumar-Junior Engineer Technical
16 PD Lansdown MDR 4662 फतेहपुर-डेरियाखाल लैन्सडोन मोटर मार्ग [ Ch. 0.000 - 18.230] 18.230 2.140 34.82 01 Apr 31 Mar 0.000 2.14 - 16 Jun 15:28 pm Mr Sachin Kumar-Junior Engineer Technical 1
17 PD Lansdown MDR 4661 सतपुली दुधारखाल धारकोट सिसल्डी मोटर मार्ग [ Ch. 0.000 - 92.000] 92.000 3.210 52.23 01 Apr 31 Mar 0.000 - - 2
18 PD Lansdown VR 4669 चखुलियाखाल ताड़केश्वर मोटर मार्ग [ Ch. 0.000 - 5.150] 5.150 3.210 47.19 01 Apr 31 Mar 0.000 3.21 - 30 Apr 15:27 pm Mr Sachin Kumar-Junior Engineer Technical
19 CD Dugadda SH 5501 स्व0 जगमोहन सिंह नेगी (लक्ष्मणझूला दुगड्डा रथुवाढाब धुमाकोट ) राज्य मार्ग [ Ch. 0.000 - 189.000] 189.000 7.490 109.95 01 Apr 31 Mar 0.000 7.49 - 02 Jun 22:41 pm Hari Singh Negi-Junior Engineer Technical 1
20 CD Dugadda MDR 4779 ढौंटियाल चपड़ेत बसड़ा मोटर मार्ग [ Ch. 0.000 - 26.500] 26.500 12.840 205.51 01 Apr 31 Mar 0.000 10.70 - 26 May 15:59 pm Hari Singh Negi-Junior Engineer Technical
21 CD Dugadda ODR 4792 किशनपुर-हरिद्वार। [ Ch. 0.000 - 1.650] 1.650 1.770 28.80 01 Apr 31 Mar 0.000 1.77 - 17 Apr 00:35 am Hari Singh Negi-Junior Engineer Technical
22 CD Dugadda VR 4805 चिल्लरखाल-हल्दूखाता मोटर मार्ग। [ Ch. 0.000 - 5.000] 5.000 2.680 39.34 01 Apr 31 Mar 0.000 - -
23 CD Baijroo VR 4947 शहीद मोहन सिंह मोटर मार्ग (मैखुली देवराडी कफलेख चौण्डा कठूरखाल मोटर मार्ग) [ Ch. 0.000 - 16.000] 16.000 1.070 15.71 01 Apr 31 Mar 0.000 1.07 - 25 Apr 17:41 pm Lokesh Kumar Saraswat-Executive Engineer Civil
24 CD Baijroo VR 4938 बीरोंखाल से डुमैला तल्ला भमरईखाल पखोली दुनाव मोटर मार्ग [ Ch. 0.000 - 10.575] 10.575 1.070 15.71 01 Apr 31 Mar 0.000 1.07 - 25 Apr 17:41 pm Lokesh Kumar Saraswat-Executive Engineer Civil 1
25 CD Paboo SH 5477 कर्णप्रयाग नौटी पैठाणी राज्य मार्ग [ Ch. 47.150 - 77.450] 30.300 5.670 92.25 01 Apr 31 Mar 0.000 4.28 - 30 May 15:50 pm Ravindra Singh Bisht-Junior Engineer Technical 14
26 CD Paboo VR 5040 श्रीकोटखाल रीठाखाल ईडा मोटर मार्ग [ Ch. 0.000 - 10.775] 10.775 5.350 87.04 01 Apr 31 Mar 0.000 5.35 - 26 May 16:16 pm Kalam Singh Negi-Executive Engineer Civil
27 PD Pauri SH 5554 टिहरी हिण्डोलाखाल देवप्रयाग व्यासघाट बिलखेत राज्य मार्ग [ Ch. 57.000 - 89.000] 32.000 18.190 295.95 06 May 31 Mar 0.000 - -
28 CD Paboo SH 5500 स्व0 श्री गीताराम पोखरियाल राज्य मार्ग (मरचूला सराईखेत बैजरो पोखडा सतपुली पौड़ी राज्य मार्ग ) [ Ch. 143.400 - 188.400] 45.000 8.560 139.27 06 May 31 Mar 0.000 - - 5
29 CD Paboo MDR 4962 सतपुली एकेश्वर जणदादेवी मोटर मार्ग [ Ch. 0.000 - 26.300] 26.300 5.350 87.04 06 May 31 Mar 0.000 - - 6
30 CD Paboo SH 5555 थलीसैण चौरीखाल चिपलघाट राज्य मार्ग [ Ch. 0.000 - 43.000] 43.000 26.750 435.22 06 May 31 Mar 0.000 - -
31 PD Pauri MDR 4381 अदवानी नाहसैंण सुरपुर बहेड़ाखाल खाण्डा मोटर मार्ग [ Ch. 0.000 - 12.000] 12.000 4.280 62.83 06 May 31 Mar 0.000 4.28 - 02 Jun 03:46 am madhavi kanojia-AE
32 PD Pauri MDR 9909 अदवानी नाहसैंण सुरपुर बहेड़ाखाल खाण्डा मोटर मार्ग [ Ch. 26.897 - 36.500] 9.603 5.350 78.54 06 May 31 Mar 0.000 - -
33 CD Baijroo SH 5557 थलीसैंण बूंगीधार देघाट जैनल मानिला डोटियाल मरचूला राज्य मार्ग [ Ch. 0.000 - 50.000] 50.000 7.810 127.07 16 Jun 31 Mar 0.000 - -