All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 1 30.41 11.63 189.22 01 Apr 2025 31 Mar 2026 0.00 11.63
MDR 3 71.12 31.03 575.98 01 Apr 2025 31 Mar 2026 0.00 18.19
4 101.53 42.66 765.20 0.00 29.82
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 CD Almora SH 5430 बागेश्वर गिरेछीना सोमेश्वर द्वाराहाट विमाण्डेश्वर ईड़ा रानीखेत राज्य मार्ग [ Ch. 20.000 - 50.410] 30.410 11.630 189.22 01 Apr 31 Mar 0.000 11.63 - 09 Jun 20:54 pm Manish Verma-Deaftsman 1
2 CD Almora MDR 5672 आरतोला जागेश्वर नैनी मोटर मार्ग [ Ch. 0.000 - 20.410] 20.410 3.210 52.23 01 Apr 31 Mar 0.000 - -
3 CD Almora MDR 7866 कोसी दौलाधाट कोरीछीना बग्वाली पोखर बिन्ता मोटर मार्ग [ Ch. 17.550 - 38.650] 21.100 18.190 367.07 01 Apr 31 Mar 0.000 18.19 - 09 Jun 20:46 pm Manish Verma-Deaftsman
4 CD Almora MDR 5769 धौलादेवी खेती जटेश्वर धुरागॉव सेराघाट मोटर मार्ग [ Ch. 0.000 - 29.605] 29.605 9.630 156.68 01 Apr 31 Mar 0.000 - -