Office :

All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 1 38.12 4.28 62.83 01 Apr 2025 31 Mar 2026 0.00 3.70
VR 12 42.35 14.89 218.72 01 Apr 2025 31 Mar 2026 0.00 9.04
13 80.47 19.17 281.55 0.00 12.74
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 CD Lohaghat SH 5999 लोहाघाट बाराकोट सिमलखेत काफलीखान भनोली राज्य मार्ग [ Ch. 0.000 - 38.120] 38.120 4.280 62.83 01 Apr 31 Mar 0.000 3.70 - 16 Jun 22:20 pm Pallavi Chaudhary-Junior Engineer Technical
2 CD Lohaghat VR 6006 लोहाघाट चैमेल मोटर मार्ग [ Ch. 0.000 - 7.500] 7.500 3.210 47.19 01 Apr 31 Mar 0.000 1.00 - 16 Jun 22:20 pm Pallavi Chaudhary-Junior Engineer Technical
3 Other VR 6024 .....मोटर मार्ग [ Ch. 0.000 - 0.100] 0.100 1.070 15.71 01 Apr 31 Mar 0.000 1.07 - 06 Jun 22:07 pm Pallavi Chaudhary-Junior Engineer Technical
4 CD Lohaghat VR 6068 पाटी जौलमेल से अस्पताल तक मोटर मार्ग [ Ch. 0.000 - 1.500] 1.500 0.540 7.94 01 Apr 31 Mar 0.000 0.54 - 19 May 20:11 pm Pallavi Chaudhary-Junior Engineer Technical
5 CD Lohaghat VR 6082 लोहाघाट पंचेश्वर मोटर मार्ग के गंगनौला से अ०जा० बस्ती बचकड़िया तक मोटर मार्ग [ Ch. 0.000 - 2.450] 2.450 0.000 0.00 01 Apr 31 Mar 0.000 - -
6 CD Lohaghat VR 6028 गर्सलेख गरसाड़ी मोटर मार्ग [ Ch. 0.000 - 6.000] 6.000 2.680 39.34 01 Apr 31 Mar 0.000 2.68 - 18 Jun 22:07 pm Pallavi Chaudhary-Junior Engineer Technical
7 CD Lohaghat VR 6007 पाटी बाजार मोटर मार्ग [ Ch. 0.000 - 0.750] 0.750 0.000 0.00 01 Apr 31 Mar 0.000 - -
8 CD Lohaghat VR 6023 टनकपुर पिथौरागढ़ मोटर मार्ग से बलाई तक मोटर मार्ग [ Ch. 0.000 - 3.000] 3.000 2.140 31.42 01 Apr 31 Mar 0.000 2.14 - 06 Jun 22:04 pm Pallavi Chaudhary-Junior Engineer Technical
9 CD Lohaghat VR 6020 अश्वाताल झलानदेव मल्ला थुवमाहरा ढेरना मंदिर तक मोटर मार्ग [ Ch. 0.000 - 6.500] 6.500 1.070 15.71 01 Apr 31 Mar 0.000 1.07 - 18 Jun 22:01 pm Pallavi Chaudhary-Junior Engineer Technical
10 CD Lohaghat VR 6058 पाटी तहसील मोटर मार्ग [ Ch. 0.000 - 0.500] 0.500 0.540 7.94 01 Apr 31 Mar 0.000 0.54 - 19 May 20:28 pm Pallavi Chaudhary-Junior Engineer Technical
11 CD Lohaghat VR 6060 किमतोली रौशाल मोटर मार्ग से अश्लाड़ मोटर मार्ग [ Ch. 0.000 - 5.000] 5.000 0.700 10.29 01 Apr 31 Mar 0.000 - -
12 CD Lohaghat VR 6095 लमताल से खर्क मोटर मार्ग [ Ch. 0.000 - 3.000] 3.000 1.070 15.73 01 Apr 31 Mar 0.000 - -
13 CD Lohaghat VR 6080 बर्दाखान-पठलती-देवराड़ी (बिसराड़ी)-आली-पट्यूड़ा मोटर मार्ग। [ Ch. 0.000 - 6.050] 6.050 1.870 27.45 16 Jun 31 Mar 0.000 - -