All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
VR 2 13.00 6.70 98.40 01 Apr 2025 31 Mar 2026 0.00 6.70
2 13.00 6.70 98.40 0.00 6.70
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 PD Champawat VR 1067 नरसिंहडॉडा गुरौली मोटर मार्ग [ Ch. 0.000 - 8.000] 8.000 4.280 62.83 01 Apr 31 Mar 0.000 4.28 - 14 May 21:14 pm Neeraj Joshi-Junior Engineer Technical
2 PD Champawat VR 1170 रीठा बिनवालगॉंव मोटर मार्ग [ Ch. 0.000 - 5.000] 5.000 2.420 35.57 01 Apr 31 Mar 0.000 2.42 - 14 May 21:15 pm Neeraj Joshi-Junior Engineer Technical