All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
MDR 1 24.00 1.07 15.71 01 Apr 2025 31 Mar 2026 0.00 0.00
VR 1 9.00 3.21 47.12 01 Apr 2025 31 Mar 2026 0.00 2.14
2 33.00 4.28 62.83 0.00 2.14
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 CD Badkote MDR 5610 डामटा कण्डारी सारीगाड़ मोटर मार्ग [ Ch. 0.000 - 24.000] 24.000 1.070 15.71 01 Apr 31 Mar 0.000 - -
2 CD Badkote VR 2087 जटा पलेठा खान्सी मोटर मार्ग। [ Ch. 0.000 - 9.000] 9.000 3.210 47.12 01 Apr 31 Mar 0.000 2.14 - 09 Jun 17:54 pm Anuj Singh-Junior Engineer Technical