All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 2 80.13 10.23 166.44 01 Apr 2025 31 Mar 2026 0.00 2.20
MDR 2 96.08 17.96 270.90 01 Apr 2025 31 Mar 2026 0.00 12.40
4 176.20 28.19 437.34 0.00 14.60
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 TD Ghansaali SH 5565 उत्तरकाशी घनसाली तिलवाडा राज्य मार्ग [ Ch. 67.125 - 129.250] 62.125 7.960 129.51 01 Apr 31 Mar 0.000 2.20 - 06 Jun 17:51 pm Dinesh Chandra Nautiyal-Executive Engineer Civil 48
2 TD Ghansaali SH 5468 जाखधार घनसाली राज्य मार्ग [ Ch. 0.000 - 18.000] 18.000 2.270 36.93 01 Apr 31 Mar 0.000 - - 33
3 TD Ghansaali MDR 5659 घनसाली कोटी अखोड़ी हुलानाखाल मुलगढ मोटर मार्ग [ Ch. 0.000 - 65.775] 65.775 13.400 196.71 01 Apr 31 Mar 0.000 12.40 - 05 Jun 01:20 am Dinesh Chandra Nautiyal-Executive Engineer Civil 5
4 TD Ghansaali MDR 5658 घनसाली घुत्तू मोटर मार्ग [ Ch. 0.000 - 30.300] 30.300 4.560 74.19 01 Apr 31 Mar 0.000 - - 3