All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 2 43.85 19.15 281.13 01 Apr 2025 31 Mar 2026 0.00 12.51
MDR 1 13.60 3.22 47.27 01 Apr 2025 31 Mar 2026 0.00 3.22
ODR 1 10.00 2.68 43.60 01 Apr 2025 31 Mar 2026 0.00 0.00
4 67.45 25.05 372.00 0.00 15.73
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 CD Chamba SH 5549 सिलक्यारा बनगांव चापड़ा सरोठ राज्य मार्ग [ Ch. 79.100 - 101.200] 22.100 13.640 200.24 01 Apr 31 Mar 0.000 7.00 - 11 Jun 17:22 pm Santosh Singh Negi-Junior Engineer Technical 14
2 CD Chamba SH 6939 डाबरखाल कुडी मौण गुरियाली रानीचौरी डांडाचली गजा नकोट पांगरखाल राज्य मार्ग [ Ch. 55.850 - 77.600] 21.750 5.510 80.89 01 Apr 31 Mar 0.000 5.51 - 27 May 18:24 pm Santosh Singh Negi-Junior Engineer Technical 9
3 CD Chamba MDR 5661 छाम मैण्डखाल बंगियाल ज्वारना मोटर मार्ग [ Ch. 0.000 - 13.600] 13.600 3.220 47.27 01 Apr 31 Mar 0.000 3.22 - 14 May 23:05 pm Santosh Singh Negi-Junior Engineer Technical 10
4 CD Chamba ODR 2658 रानीचौरी नकोट मोटर मार्ग [ Ch. 0.000 - 10.000] 10.000 2.680 43.60 01 Apr 31 Mar 0.000 - - 4