Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
VR 3 29.40 8.99 132.05 01 Apr 2025 31 Mar 2026 0.00 8.99
ODR 1 19.00 4.28 62.83 01 Apr 2025 31 Mar 2026 0.00 4.28
4 48.40 13.27 194.88 0.00 13.27
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 TD Kirtinagar VR 2749 हिण्डोलाखाल पलेठी बनगढ़ मोटर मार्ग [ Ch. 0.000 - 10.000] 10.000 3.210 47.19 01 Apr 31 Mar 0.000 3.21 - 10 Jun 17:06 pm Arvind Dyundi-Junior Engineer Technical
2 TD Kirtinagar VR 2766 लक्षमोली से तल्याकोट तक मोटर मार्ग [ Ch. 0.000 - 2.000] 2.000 2.140 31.42 01 Apr 31 Mar 0.000 2.14 - 18 May 00:17 am Arvind Dyundi-Junior Engineer Technical 3
3 TD Kirtinagar VR 2755 रामपुर श्यामपुर बमाणा मोटर मार्ग [ Ch. 0.000 - 17.400] 17.400 3.640 53.44 01 Apr 31 Mar 0.000 3.64 - 17 May 01:49 am Arvind Dyundi-Junior Engineer Technical 20
4 TD Kirtinagar ODR 2771 नागचौड़ चामी तोली पीपलीधार मोटर मार्ग [ Ch. 0.000 - 19.000] 19.000 4.280 62.83 01 Apr 31 Mar 0.000 4.28 - 19 May 00:48 am Arvind Dyundi-Junior Engineer Technical 11