All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
ODR 2 17.50 9.78 139.17 01 Apr 2025 31 Mar 2026 0.00 7.85
MDR 2 45.60 35.99 512.19 26 May 2025 31 Mar 2026 0.00 0.00
4 63.10 45.77 651.36 0.00 7.85
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 PD Dehradun ODR 2940 रेसकोर्स कालोनी के आन्तरिक मार्ग [ Ch. 0.000 - 1.500] 1.500 1.930 27.46 01 Apr 31 Mar 0.000 - - 1
2 PD Dehradun ODR 2956 छरबा होरावाला नाहड़ मोटर मार्ग [ Ch. 0.000 - 16.000] 16.000 7.850 111.71 01 Apr 31 Mar 0.000 7.85 - 06 May 19:28 pm Sardar Singh Rawat-Junior Engineer Technical 7
3 PD Dehradun MDR 5675 सहसपुर शंकरपुर रमसावाला भाउवाला सुद्धोवाला मोटर मार्ग [ Ch. 0.000 - 20.600] 20.600 19.710 280.53 26 May 31 Mar 0.000 - -
4 PD Dehradun MDR 5669 सेलाकुई भाउवाला डूंगा नन्दा की चौकी मोटर मार्ग [ Ch. 0.000 - 25.000] 25.000 16.280 231.66 26 May 31 Mar 0.000 - - 1