Back

Office :

All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 2 119.50 46.66 567.66 01 Apr 2025 31 Mar 2026 0.00 0.00
VR 2 7.60 6.53 95.86 01 Apr 2025 31 Mar 2026 1.18 5.35 453.39 %
4 127.10 53.19 663.52 1.18 5.35 453.39 %