All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 2 81.00 26.04 423.67 01 Apr 2025 31 Mar 2026 0.00 7.85
VR 4 9.94 5.57 81.88 01 Apr 2025 31 Mar 2026 0.00 2.00
MDR 2 21.60 9.63 141.37 06 May 2025 31 Mar 2026 0.00 4.28
8 112.54 41.24 646.92 0.00 14.13
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 PD Pauri SH 5519 पौड़ी देवप्रयाग गजा जाजल राज्य मार्ग [ Ch. 0.000 - 49.000] 49.000 7.850 127.72 01 Apr 31 Mar 0.000 7.85 - 09 May 16:46 pm Mr Devpal Singh Rawat-Junior Engineer Technical 15
2 PD Pauri VR 4413 पौडी देवप्रयाग मोटर मार्ग से सूनर गदेरा सल्डा मार्ग [ Ch. 0.000 - 2.640] 2.640 2.830 41.60 01 Apr 31 Mar 0.000 2.00 - 18 Jun 18:57 pm madhavi kanojia-AE
3 PD Pauri VR 4466 बडोली बैण्ड से मन्दिर तक मोटर मार्ग [ Ch. 0.000 - 0.400] 0.400 0.430 6.32 01 Apr 31 Mar 0.000 - -
4 PD Pauri VR 4475 घोडीखाल गोदी गदना भिमली आलधार मोटर मार्ग [ Ch. 0.000 - 6.250] 6.250 1.610 23.67 01 Apr 31 Mar 0.000 - -
5 PD Pauri VR 4490 रामकुण्ड में पौडी देवप्रयाग मोटर मार्ग से देवप्रयाग इण्टर कालेज से खेडा तक मोटर मार्ग [ Ch. 0.000 - 0.650] 0.650 0.700 10.29 01 Apr 31 Mar 0.000 - -
6 PD Pauri SH 5554 टिहरी हिण्डोलाखाल देवप्रयाग व्यासघाट बिलखेत राज्य मार्ग [ Ch. 57.000 - 89.000] 32.000 18.190 295.95 06 May 31 Mar 0.000 - -
7 PD Pauri MDR 4381 अदवानी नाहसैंण सुरपुर बहेड़ाखाल खाण्डा मोटर मार्ग [ Ch. 0.000 - 12.000] 12.000 4.280 62.83 06 May 31 Mar 0.000 4.28 - 02 Jun 03:46 am madhavi kanojia-AE
8 PD Pauri MDR 9909 अदवानी नाहसैंण सुरपुर बहेड़ाखाल खाण्डा मोटर मार्ग [ Ch. 26.897 - 36.500] 9.603 5.350 78.54 06 May 31 Mar 0.000 - -