Back

Office :

All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
VR 5 47.42 22.47 329.97 01 Apr 2025 31 Mar 2026 0.00 17.81
5 47.42 22.47 329.97 0.00 17.81
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 CD Pauri VR 8582 पोखर खुर्कताल मोटर मार्ग [ Ch. 0.000 - 21.070] 21.070 5.350 78.54 01 Apr 31 Mar 0.000 5.35 - 11 Jun 15:21 pm Mr Vikash Bisht-Junior Engineer Technical
2 CD Pauri VR 8579 सीकू कणडेरी मोटर मोटर मार्ग [ Ch. 0.000 - 9.000] 9.000 6.420 94.25 01 Apr 31 Mar 0.000 3.90 - 11 Jun 15:21 pm Mr Vikash Bisht-Junior Engineer Technical
3 CD Pauri VR 4565 चौबट्टाखाल दांथा मोटर मार्ग [ Ch. 0.000 - 7.350] 7.350 6.420 94.34 01 Apr 31 Mar 0.000 4.28 - 11 Jun 15:21 pm Mr Vikash Bisht-Junior Engineer Technical
4 CD Pauri VR 4596 असनोली ओणी खण्डाह मोटर मार्ग [ Ch. 0.000 - 5.000] 5.000 2.140 31.42 01 Apr 31 Mar 0.000 2.14 - 01 May 16:16 pm Mr Vikash Bisht-Junior Engineer Technical
5 CD Pauri VR 4556 शहीद नेत्र सिंह मोटर मार्ग (तैला बारे मोटर मार्ग) [ Ch. 0.000 - 5.000] 5.000 2.140 31.42 01 Apr 31 Mar 0.000 2.14 - 23 Apr 17:55 pm Mr Vikash Bisht-Junior Engineer Technical