All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 1 32.22 21.73 326.66 01 Apr 2025 31 Mar 2026 0.00 0.00
VR 2 23.03 5.35 78.88 01 Apr 2025 31 Mar 2026 0.00 5.35
3 55.25 27.08 405.54 0.00 5.35
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 CD Srinagar SH 5488 पौड़ी खिर्सू खेडाखाल खांखरा राज्य मार्ग [ Ch. 0.000 - 32.220] 32.220 21.730 326.66 01 Apr 31 Mar 0.000 - -
2 CD Srinagar VR 4618 डबरूखाल मोलखाखाल टीला मोटर मार्ग [ Ch. 0.000 - 19.025] 19.025 4.280 62.83 01 Apr 31 Mar 0.000 4.28 - 02 Jun 19:28 pm Veer Singh-JET
3 CD Srinagar VR 4612 रामपुर गवाणा मोटर मार्ग [ Ch. 0.000 - 4.000] 4.000 1.070 16.05 01 Apr 31 Mar 0.000 1.07 - 01 May 15:54 pm Veer Singh-JET 7