Office :

All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 2 182.60 12.31 200.28 01 Apr 2025 31 Mar 2026 0.00 12.31
MDR 2 110.23 5.35 87.05 01 Apr 2025 31 Mar 2026 0.00 2.14
VR 1 5.15 3.21 47.19 01 Apr 2025 31 Mar 2026 0.00 3.21
5 297.98 20.87 334.52 0.00 17.66
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 PD Lansdown SH 5591 शहीद संदीप सिंह रावत राज्य मार्ग (घटटूगाड सिलोगी गुमखाल लैंसडौन डेरियाखाल रिखणीखाल बीरौंखाल मोटर मार्ग ) [ Ch. 14.500 - 169.600] 155.100 2.680 43.60 01 Apr 31 Mar 0.000 2.68 - 05 Jun 22:52 pm Mr Sachin Kumar-Junior Engineer Technical 1
2 PD Lansdown SH 5502 स्व0 जगमोहन सिंह नेगी (लक्ष्मणझूला दुगड्डा रथुवाढाब धुमाकोट ) राज्य मार्ग [ Ch. 189.000 - 216.500] 27.500 9.630 156.68 01 Apr 31 Mar 0.000 9.63 - 16 Jun 15:28 pm Mr Sachin Kumar-Junior Engineer Technical
3 PD Lansdown MDR 4662 फतेहपुर-डेरियाखाल लैन्सडोन मोटर मार्ग [ Ch. 0.000 - 18.230] 18.230 2.140 34.82 01 Apr 31 Mar 0.000 2.14 - 16 Jun 15:28 pm Mr Sachin Kumar-Junior Engineer Technical 1
4 PD Lansdown MDR 4661 सतपुली दुधारखाल धारकोट सिसल्डी मोटर मार्ग [ Ch. 0.000 - 92.000] 92.000 3.210 52.23 01 Apr 31 Mar 0.000 - - 2
5 PD Lansdown VR 4669 चखुलियाखाल ताड़केश्वर मोटर मार्ग [ Ch. 0.000 - 5.150] 5.150 3.210 47.19 01 Apr 31 Mar 0.000 3.21 - 30 Apr 15:27 pm Mr Sachin Kumar-Junior Engineer Technical