Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
MDR 2 28.80 5.00 11.00 20 Sep 2025 31 Oct 2025 4.97 5.00 100.60 %
ODR 2 9.00 6.00 8.00 20 Sep 2025 31 Oct 2025 5.95 6.00 100.84 %
4 37.80 11.00 19.00 10.92 11.00 100.73 %
Division Type Div Seg ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 CD Kapkot MDR 5609 कपकोट कर्मी मोटर मार्ग [ Ch. 0.000 - 21.800] 21.800 3.000 7.00 20 Sep 31 Oct 2.980 3.00 101 05 Oct 16:16 pm Ankur Singh, Assistant Engineer Civil, CD Kapkot 7
2 CD Kapkot MDR 265 भयू गदैरा नरगडा तक मोटर मार्ग [ Ch. 0.000 - 7.000] 7.000 2.000 4.00 20 Sep 31 Oct 1.990 2.00 101 06 Oct 10:45 am Ankur Singh, Assistant Engineer Civil, CD Kapkot 57
3 CD Kapkot ODR 5763 बैड़ा पाखड़ ओखलधार से दोफाड़ मोटर मार्ग [ Ch. 8.000 - 16.000] 8.000 5.000 6.00 20 Sep 31 Oct 4.960 5.00 101 15 Oct 18:44 pm Ankur Singh, Assistant Engineer Civil, CD Kapkot 14
4 CD Kapkot ODR 260 चौरा गाँव तक पहुॅच मार्ग [ Ch. 0.000 - 1.000] 1.000 1.000 2.00 20 Sep 31 Oct 0.990 1.00 101 02 Oct 18:33 pm Ankur Singh, Assistant Engineer Civil, CD Kapkot