Patch Repair 2025-26 (Post-Mansoon) • Progress Report
| # | Division | Type | ID | Name | Total Len | Target | Amount | Start | End | Calc. Target | Progress | % | Date | By | Imgs |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | PD Gopeshwar | SH | 5521 |
रुद्रप्रयाग पोखरी गोपेश्वर राज्य मार्ग
Ch. 87.320 - 111.720
|
24.400 | 24.000 | 10.00 | 20 Sep | 31 Oct | 24.000 | 24.40 | 102 | 16 Oct 08:55 | Prashant Rawat, Assistant Engineer Civil, PD Gopeshwar | 68 |
| 2 | PD Gopeshwar | SH | 5470 |
जोशीमठ सिंहधार नृसिंह मंदिर राज्य मार्ग
Ch. 0.000 - 3.900
|
3.900 | 3.000 | 5.00 | 20 Sep | 31 Oct | 3.000 | 3.00 | 100 | 23 Oct 12:51 | Himanshu Bhatt, Assistant Engineer Civil, PD Gopeshwar | 15 |
| 3 | PD Gopeshwar | MDR | 5956 |
स्वतंत्रता संग्राम सेनानी शहीद बुद्धि सिंह पंवार लीसा फैक्ट्री गोपेश्वर देवरखड़ोरा मोटर मार्ग
Ch. 0.000 - 11.750
|
11.750 | 11.000 | 8.00 | 20 Sep | 31 Oct | 11.000 | 11.00 | 100 | 23 Oct 13:59 | Umesh Dharia, Assistant Engineer Civil, PD Gopeshwar | 20 |
| 4 | PD Gopeshwar | ODR | 329 |
गोपेश्वर के आन्तरिक मोटर मार्ग
Ch. 0.000 - 4.800
|
4.800 | 4.000 | 2.00 | 20 Sep | 31 Oct | 4.000 | 4.00 | 100 | 30 Sep 16:24 | Umesh Dharia, Assistant Engineer Civil, PD Gopeshwar | |
| 5 | PD Gopeshwar | ODR | 341 |
नन्दप्रयाग चमोली वाया सावरीसैंण मोटर मार्ग (चारधाम यात्रा का वैकल्पिक मार्ग )
Ch. 0.000 - 11.000
|
11.000 | 11.000 | 8.00 | 20 Sep | 31 Oct | 11.000 | 11.00 | 100 | 25 Sep 15:15 | Prashant Rawat, Assistant Engineer Civil, PD Gopeshwar | 26 |