PD Gopeshwar

Patch Repair 2025-26 (Post-Mansoon) • Progress Report

Summary by Road Type

All Length in KM and Amount in Rs. Lacs
Select Road Type Segments Total Len Target Amount Start Date End Date Calc. Target Progress % Achieved
SH 2 28.30 27.00 15.00 20 Sep 2025 31 Oct 2025 27.00 27.40 101.48
MDR 1 11.75 11.00 8.00 20 Sep 2025 31 Oct 2025 11.00 11.00 100
ODR 2 15.80 15.00 10.00 20 Sep 2025 31 Oct 2025 15.00 15.00 100
Total 5 55.85 53.00 33.00 53.00 53.40 100.75

Detailed Report

# Division Type ID Name Total Len Target Amount Start End Calc. Target Progress % Date By Imgs
1 PD Gopeshwar SH 5521
रुद्रप्रयाग पोखरी गोपेश्वर राज्य मार्ग
Ch. 87.320 - 111.720
24.400 24.000 10.00 20 Sep 31 Oct 24.000 24.40 102 16 Oct 08:55 Prashant Rawat, Assistant Engineer Civil, PD Gopeshwar 68
2 PD Gopeshwar SH 5470
जोशीमठ सिंहधार नृसिंह मंदिर राज्य मार्ग
Ch. 0.000 - 3.900
3.900 3.000 5.00 20 Sep 31 Oct 3.000 3.00 100 23 Oct 12:51 Himanshu Bhatt, Assistant Engineer Civil, PD Gopeshwar 15
3 PD Gopeshwar MDR 5956
स्वतंत्रता संग्राम सेनानी शहीद बुद्धि सिंह पंवार लीसा फैक्ट्री गोपेश्वर देवरखड़ोरा मोटर मार्ग
Ch. 0.000 - 11.750
11.750 11.000 8.00 20 Sep 31 Oct 11.000 11.00 100 23 Oct 13:59 Umesh Dharia, Assistant Engineer Civil, PD Gopeshwar 20
4 PD Gopeshwar ODR 329
गोपेश्वर के आन्तरिक मोटर मार्ग
Ch. 0.000 - 4.800
4.800 4.000 2.00 20 Sep 31 Oct 4.000 4.00 100 30 Sep 16:24 Umesh Dharia, Assistant Engineer Civil, PD Gopeshwar
5 PD Gopeshwar ODR 341
नन्दप्रयाग चमोली वाया सावरीसैंण मोटर मार्ग (चारधाम यात्रा का वैकल्पिक मार्ग )
Ch. 0.000 - 11.000
11.000 11.000 8.00 20 Sep 31 Oct 11.000 11.00 100 25 Sep 15:15 Prashant Rawat, Assistant Engineer Civil, PD Gopeshwar 26