PD Nainital

Patch Repair 2025-26 (Post-Mansoon) • Progress Report

Summary by Road Type

All Length in KM and Amount in Rs. Lacs
Select Road Type Segments Total Len Target Amount Start Date End Date Calc. Target Progress % Achieved
SH 3 108.09 33.09 50.00 20 Sep 2025 31 Oct 2025 33.09 33.09 100
MDR 2 29.33 17.50 19.00 20 Sep 2025 31 Oct 2025 17.50 17.50 100
ODR 1 13.00 4.40 6.00 20 Sep 2025 31 Oct 2025 4.40 4.40 100
Total 6 150.42 54.99 75.00 54.99 54.99 100

Detailed Report

# Division Type ID Name Total Len Target Amount Start End Calc. Target Progress % Date By Imgs
1 PD Nainital SH 5440
भवाली नैनीताल टॉकी किलबरी पंगोट किलबरी राज्य मार्ग
Ch. 0.000 - 26.430
26.430 8.430 15.00 20 Sep 31 Oct 8.430 8.43 100 15 Oct 15:52 Manoj Kumar Pande, Assistant Engineer Civil, PD Nainital
2 PD Nainital SH 432
काठगोदाम हैड़ाखान साननी बैण्ड सिमलिया बैण्ड राज्य मार्ग
Ch. 0.000 - 50.000
50.000 10.000 20.00 20 Sep 31 Oct 10.000 10.00 100 15 Oct 15:53 Manoj Kumar Pande, Assistant Engineer Civil, PD Nainital 2
3 PD Nainital SH 5512
नैनीताल कालाढूगी बाजपुर दोराहा राज्य मार्ग
Ch. 0.000 - 31.660
31.660 14.660 15.00 20 Sep 31 Oct 14.660 14.66 100 15 Oct 15:53 Manoj Kumar Pande, Assistant Engineer Civil, PD Nainital 3
4 PD Nainital MDR 7848
अमृतपुर बनना बबियाड़ मोटर मार्ग
Ch. 0.000 - 22.825
22.825 13.000 12.00 20 Sep 31 Oct 13.000 13.00 100 20 Oct 14:44 Manoj Kumar Pande, Assistant Engineer Civil, PD Nainital
5 PD Nainital MDR 7847
नैनीताल बाईपास मोटर मार्ग
Ch. 0.000 - 6.500
6.500 4.500 7.00 20 Sep 31 Oct 4.500 4.50 100 14 Oct 13:23 Ratnesh Kumar Saxena, Executive Engineer Civil, PD Nainital
6 PD Nainital ODR 438
घुघुखान सौड मोटर मार्ग
Ch. 0.000 - 13.000
13.000 4.400 6.00 20 Sep 31 Oct 4.400 4.40 100 21 Oct 10:29 Ratnesh Kumar Saxena, Executive Engineer Civil, PD Nainital