Back

Office :

All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 3 108.09 33.09 50.00 20 Sep 2025 31 Oct 2025 32.86 33.09 100.70 %
MDR 2 29.33 17.50 19.00 20 Sep 2025 31 Oct 2025 17.38 17.50 100.69 %
ODR 1 13.00 4.40 6.00 20 Sep 2025 31 Oct 2025 4.37 4.40 100.69 %
6 150.42 54.99 75.00 54.61 54.99 100.70 %
Division Type Div Seg ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 PD Nainital SH 5440 भवाली नैनीताल टॉकी किलबरी पंगोट किलबरी राज्य मार्ग [ Ch. 0.000 - 26.430] 26.430 8.430 15.00 20 Sep 31 Oct 8.370 8.43 101 15 Oct 15:34 pm Manoj Kumar Pande, Assistant Engineer Civil, PD Nainital
2 PD Nainital SH 432 काठगोदाम हैड़ाखान साननी बैण्ड सिमलिया बैण्ड राज्य मार्ग [ Ch. 0.000 - 50.000] 50.000 10.000 20.00 20 Sep 31 Oct 9.930 10.00 101 15 Oct 15:35 pm Manoj Kumar Pande, Assistant Engineer Civil, PD Nainital 2
3 PD Nainital SH 5512 नैनीताल कालाढूगी बाजपुर दोराहा राज्य मार्ग [ Ch. 0.000 - 31.660] 31.660 14.660 15.00 20 Sep 31 Oct 14.560 14.66 101 15 Oct 15:35 pm Manoj Kumar Pande, Assistant Engineer Civil, PD Nainital 3
4 PD Nainital MDR 7848 अमृतपुर बनना बबियाड़ मोटर मार्ग [ Ch. 0.000 - 22.825] 22.825 13.000 12.00 20 Sep 31 Oct 12.910 13.00 101 20 Oct 14:26 pm Manoj Kumar Pande, Assistant Engineer Civil, PD Nainital
5 PD Nainital MDR 7847 नैनीताल बाईपास मोटर मार्ग [ Ch. 0.000 - 6.500] 6.500 4.500 7.00 20 Sep 31 Oct 4.470 4.50 101 14 Oct 13:05 pm Ratnesh Kumar Saxena, Executive Engineer Civil, PD Nainital
6 PD Nainital ODR 438 घुघुखान सौड मोटर मार्ग [ Ch. 0.000 - 13.000] 13.000 4.400 6.00 20 Sep 31 Oct 4.370 4.40 101 21 Oct 10:11 am Ratnesh Kumar Saxena, Executive Engineer Civil, PD Nainital