Patch Repair 2025-26 (Post-Mansoon) • Progress Report

Summary by Road Type

All Length in KM and Amount in Rs. Lacs
Select Road Type Segments Total Len Target Amount Start Date End Date Calc. Target Progress % Achieved
SH 2 37.50 12.50 28.00 20 Sep 2025 31 Oct 2025 12.50 12.50 100
ODR 2 3.58 1.72 5.00 20 Sep 2025 31 Oct 2025 1.72 1.92 111.63
Total 4 41.08 14.22 33.00 14.22 14.42 101.41

Detailed Report

# Division Type ID Name Total Len Target Amount Start End Calc. Target Progress % Date By Imgs
1 PD Didihaat SH 5428
अल्मोेड़ा बेरीनाग थल मुवानी चैबाटी सानदेव डीडीहाट ओगला राज्य मार्ग
Ch. 0.000 - 19.500
19.500 5.500 10.00 20 Sep 31 Oct 5.500 5.50 100 23 Oct 13:49 Tara Singh, Assistant Engineer Civil, PD Didihaat
2 PD Didihaat SH 5429
अल्मोेड़ा बेरीनाग थल पमतोड़ी भातड़ सानदेव डीडीहाट ओगला राज्य मार्ग
Ch. 0.000 - 18.000
18.000 7.000 18.00 20 Sep 31 Oct 7.000 7.00 100 23 Oct 13:50 Tara Singh, Assistant Engineer Civil, PD Didihaat
3 PD Didihaat ODR 905
डीडीहाट में आन्तरिक मार्ग
Ch. 0.000 - 2.860
2.860 1.000 2.50 20 Sep 31 Oct 1.000 1.20 120 16 Oct 17:46 Ajay Chandra Upreti, Assistant Engineer Civil, PD Didihaat
4 PD Didihaat ODR 907
तेजम बाजार पहुंच मार्ग
Ch. 0.000 - 0.720