Back

Office :

All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 2 37.50 12.50 28.00 20 Sep 2025 31 Oct 2025 12.41 12.50 100.73 %
ODR 2 3.58 1.72 5.00 20 Sep 2025 31 Oct 2025 1.70 1.92 112.94 %
4 41.08 14.22 33.00 14.11 14.42 102.20 %
Division Type Div Seg ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 PD Didihaat SH 5428 अल्मोेड़ा बेरीनाग थल मुवानी चैबाटी सानदेव डीडीहाट ओगला राज्य मार्ग [ Ch. 0.000 - 19.500] 19.500 5.500 10.00 20 Sep 31 Oct 5.460 5.50 101 23 Oct 13:31 pm Tara Singh, Assistant Engineer Civil, PD Didihaat
2 PD Didihaat SH 5429 अल्मोेड़ा बेरीनाग थल पमतोड़ी भातड़ सानदेव डीडीहाट ओगला राज्य मार्ग [ Ch. 0.000 - 18.000] 18.000 7.000 18.00 20 Sep 31 Oct 6.950 7.00 101 23 Oct 13:32 pm Tara Singh, Assistant Engineer Civil, PD Didihaat
3 PD Didihaat ODR 905 डीडीहाट में आन्तरिक मार्ग [ Ch. 0.000 - 2.860] 2.860 1.000 2.50 20 Sep 31 Oct 0.990 1.20 121 16 Oct 17:28 pm Ajay Chandra Upreti, Assistant Engineer Civil, PD Didihaat
4 PD Didihaat ODR 907 तेजम बाजार पहुंच मार्ग [ Ch. 0.000 - 0.720] 0.720 0.720 2.50 20 Sep 31 Oct 0.710 0.72 101 14 Oct 09:54 am Tara Singh, Assistant Engineer Civil, PD Didihaat