Patch Repair 2025-26 (Post-Mansoon) • Progress Report
| # | Division | Type | ID | Name | Total Len | Target | Amount | Start | End | Calc. Target | Progress | % | Date | By | Imgs |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | CD Askote | SH | 5516 |
ओगला से भागीचैरा पस्मा हंसेश्वर राज्य मार्ग
Ch. 0.000 - 8.700
|
8.700 | 4.000 | 7.00 | 20 Sep | 31 Oct | 4.000 | 4.00 | 100 | 10 Oct 11:51 | Jagat Singh Bora, Assistant Engineer Civil, CD Askote | 6 |
| 2 | CD Askote | SH | 5456 |
देवलथल कनालीछीना से न्वाली पीपली द्वालीसेरा राज्य मार्ग
Ch. 0.000 - 5.600
|
5.600 | 4.000 | 7.00 | 20 Sep | 31 Oct | 4.000 | 4.00 | 100 | 26 Sep 14:04 | Jagat Singh Bora, Assistant Engineer Civil, CD Askote | 3 |
| 3 | CD Askote | MDR | 5692 |
तवाघाट नारायण आश्रम मोटर मार्ग
Ch. 0.000 - 27.025
|
27.025 | 11.000 | 19.25 | 20 Sep | 31 Oct | 11.000 | 18.00 | 164 | 19 Dec 14:33 | Ashish Lunthi, Assistant Engineer Civil, CD Askote | |
| 4 | CD Askote | ODR | 1024 |
आन्तरिक मार्ग धारचूला
Ch. 0.000 - 2.360
|
2.360 | 2.360 | 4.13 | 20 Sep | 31 Oct | 2.360 | 2.36 | 100 | 14 Oct 09:14 | Ashish Lunthi, Assistant Engineer Civil, CD Askote | 21 |