Loading Dashboard...

Back

CD Lohaghat

Patch Repair 2025-26 (Post-Mansoon) • Progress Report

Summary by Road Type

All Length in KM and Amount in Rs. Lacs
Select Road Type Segments Total Len Target Amount Start Date End Date Calc. Target Progress % Achieved
SH 3 133.92 69.00 80.00 20 Sep 2025 31 Oct 2025 69.00 69.00 100
MDR 1 18.00 14.00 21.00 20 Sep 2025 31 Oct 2025 14.00 14.00 100
ODR 1 14.60 11.00 16.00 20 Sep 2025 31 Oct 2025 11.00 11.00 100
Total 5 166.52 94.00 117.00 94.00 94.00 100

Detailed Report

# Division Type ID Name Total Len Target Amount Start End Calc. Target Progress % Date By Imgs
1 CD Lohaghat SH 5569
काठगोदाम (रानीबाग) भीमताल खुटानी चांफी पदमपुरी धानाचूली पहाड़पानी शहरफाटक मौरनौला देवीधुरा लोहाघाट पंचेश्वर राज्य मार्ग
Ch. 147.200 - 188.800
41.600 10.000 12.00 20 Sep 31 Oct 10.000 10.00 100 19 Oct 16:26 Harish Singh Bathiyal, Assistant Engineer Civil, CD Lohaghat 1
2 CD Lohaghat SH 5485
काठगोदाम (रानीबाग) भीमताल खुटानी चांफी पदमपुरी धानाचूली पहाड़पानी शहरफाटक मौरनौला देवीधुरा लोहाघाट पंचेश्वर राज्य मार्ग
Ch. 92.400 - 146.600
54.200 38.000 38.00 20 Sep 31 Oct 38.000 38.00 100 17 Oct 15:49 Pankaj Singh Bhandari, Assistant Engineer Civil, Engineer-in-Chief Office
3 CD Lohaghat SH 5999
लोहाघाट बाराकोट सिमलखेत काफलीखान भनोली राज्य मार्ग
Ch. 0.000 - 38.120
38.120 21.000 30.00 20 Sep 31 Oct 21.000 21.00 100 19 Oct 16:17 Pankaj Singh Bhandari, Assistant Engineer Civil, Engineer-in-Chief Office
4 CD Lohaghat MDR 5684
किमतोली रौशाल मोटर मार्ग
Ch. 0.000 - 18.000
18.000 14.000 21.00 20 Sep 31 Oct 14.000 14.00 100 19 Oct 16:26 Harish Singh Bathiyal, Assistant Engineer Civil, CD Lohaghat 2
5 CD Lohaghat ODR 6001
किमतोली पुल्ला चमदेवल जाख निडिल मोटर मार्ग
Ch. 0.000 - 14.600
14.600 11.000 16.00 20 Sep 31 Oct 11.000 11.00 100 19 Oct 16:26 Harish Singh Bathiyal, Assistant Engineer Civil, CD Lohaghat 2